Infrastructure

San Juan Pilots Again Delay Amur River LNG Tanker Entry Over Wind Speeds

Published Oct 12, 2026, 10:15 AM ASTvia El Nuevo Día

Also reported by NotiUno.

At a glance

  • The San Juan Bay Pilots Association will not guide the Amur River if the wind exceeds 10 knots.
  • NFE is evaluating alternatives to safely receive the tanker, including reorganizing the sequence of vessels or using additional piloting resources.
  • A federal judge authorized the entry of the Amur River on October 1, ordering NFE to pay for additional tugboats required for the operation.

Entry of the liquefied natural gas (LNG) tanker Amur River into San Juan Bay was suspended again on Monday, October 12, because of wind speeds at the bay entrance, delaying natural gas for Puerto Rico Electric Power Authority (PREPA (AEE), or PREPA) plants that have spent weeks running on a costlier fuel. Around 12:30 PM, New Fortress Energy (NFE) was told the San Juan pilots would not guide the vessel; maneuvers had been set to begin at 11:30 AM. The San Juan Bay Pilots Association told the federal court it would guide the tanker only if wind was below 10 knots.

Winds at the bay entrance measured between 13 and 15 knots at the time of the cancellation, per NFE’s monitoring, and 10.55 knots at 11:00 AM. NFE had asked for entry between 6:00 and 10:00 AM and said the pilots’ schedule included 10 vessels in the window it considered favorable. Forecasts suggest favorable winds around 6:00 PM. Monday; otherwise NFE would ask for entry on Tuesday.

The Amur River carries gas for units 5 and 6 of the San Juan plant, now running on diesel, and for temporary generation units at Palo Seco and San Juan. U.S. Customs and Border Protection authorized entry Monday morning, and the Coast Guard confirmed authorization Sunday. The tanker was due to dock September 16.

Federal Judge Silvia Carreño Coll authorized its entry on October 1, ordering NFE to pay for additional tugboats. On Tuesday, Judge María Antongiorgi Jordán will preside over a hearing in a case brought for PREPA by the Independent Procurement Office (3PPO) seeking to activate contract clauses allowing a third party to deliver gas to NFE’s terminal.

In context — 787daily, from public data

  • LUMA's portal showed under 0.1% of customers out at 6:07 AM AST on Oct 12, 2026. Across the 36 days 787daily has tracked it, the daily average is 0.3% and the worst was 1.8% on Sep 30, 2026.

    LUMA Energy outage portal, read each morning by 787daily · Oct 12, 6:07 AM AST
  • Customers in LUMA's San Juan region averaged 29.6 hours without power in the fiscal year that ended in June 2026, against 28.4 hours island-wide.

    LUMA operates the transmission and distribution system. A LUMA region is a utility district named for its hub town, not that town alone.

    PR Energy Bureau — SAIDI as filed by LUMA · fiscal year ending June 2026
  • San Juan

    336,160ACS 2020–2024 estimate1521Founded47.9 sq mi (124 km²)Area
SourceEl Nuevo Día

Follow this story

  1. · El Nuevo DíaLNG Tanker Amur River’s San Juan Bay Entry Delayed to Monday Amid Customs and Wind Limits
  2. · Telemundo PRAmur River’s San Juan Port Entry Canceled Due to Strong Winds
  3. · NotiUnoFormer House Speaker Accuses New Fortress Energy of 'Blackmailing' Puerto Rico Over Amur River Gas Ship
Full timeline