As of the U.S. Drought Monitor map for the week of September 15: 60 of Puerto Rico’s 78 municipios are in moderate drought or worse, 53 of them severe or worse, and AAA's metro water rotation is paused in the San Juan metro area — since September 2, though AAA has not cancelled the plan.
Where things stand
CarraízoSafe
40.79 m
−2 cm since yesterday
Rising 25.7 cm a day this week — on track to reach Spilling in ~1 days (Sep 22)
La PlataAdjustments
44.70 m
+4 cm since yesterday
Rising 4 cm a day this week — on track to reach Watch in ~5 days (Sep 26)
CidraWatch
400.54 m
unchanged since yesterday
Rising 4.5 cm a day this week — 0.31 m above the Adjustments line
Rain nearby this week: 3.59 in near Carraízo, 1.34 in near La Plata, 4.45 in near Cidra, most of it on Sep 16.
AAA · reservoirs · Carraízo & La Plata · Sep 14: We followed the drought conditions in Puerto Rico during the drought committee meeting. The rains recorded this week…
AAA · reservoirs · Cidra · Sep 11: Our teams have completed the repair work of an outlet in #Cidra. Our brigades continue to work to reduce water losses…
What to watch
- Carraízo: whether the rise survives a dry week — this week's gain came with 3.59 in of rain nearby.
- La Plata: whether the rise survives a dry week — this week's gain came with 1.34 in of rain nearby.
- Cidra: whether the rise survives a dry week — this week's gain came with 4.45 in of rain nearby.
AAA’s 5 AM chart, USGS gauges; rates and pace dates are arithmetic, not forecasts.
Service rotation — Sergio Cuevas Bustamante filtration plant (Trujillo Alto)
Phase 1 — 48-hour rotations
Interruptions paused since September 2 — AAA has not cancelled the plan
Both zones have water. What follows is AAA’s published calendar — the schedule that would apply if the rotation resumes; AAA decides that, and we update this page when it does.
AAA has not mentioned the plan in 19 days. Its last press release on the rotation was August 14, and the plan is still published. Checked automatically against AAA’s plan page, press releases and notices.
What the Governor and AAA said, and where
Scheduled interruptions PAUSED. Gov. Jenniffer González Colón announced on the evening of Sept. 1 a 48–72 hour pause for Carraízo customers (Zones 1 and 2) after the reservoir rose past the observación line. AAA never cancelled the plan and has never announced its resumption either, so the pause has now outlasted its announced length many times over. RE-VERIFIED 2026-09-17 against AAA's own channels, all four of which say the same thing by saying nothing: the plan page still publishes the Sergio Cuevas plan and its PDF is unchanged since Aug. 5 (no revision, no cancellation); AAA's press-release archive has not mentioned the metro rotation since Aug. 8, with the newest releases (Sept. 10–15) about other plants entirely; @AcueductosPR's last 50 posts carry no Zone 1 or Zone 2 interruption notice; and AAA's own Sept. 14 drought-committee post reports rain raising Carraízo and La Plata with no mention of resuming. Carraízo stood at 40.06 m that morning — the seguridad band, 0.36 m below desborde and up 0.99 m in seven days. NOTE WHAT THIS IS NOT: AAA has not SAID the rotation is over, and an absence of notices is not an announcement. Treat the plan as dormant, not ended, and verify with AAA before planning around it.
Sources: AAA — Planes de Interrupciones Programadas 2026 (checked 2026-09-17: plan still published, PDF Last-Modified 2026-08-05, no revision or cancellation) · AAA — Archivo de comunicados de prensa (checked 2026-09-17: nothing on the metro rotation since Aug. 8; newest releases Sept. 10–15 concern other plants) · Primera Hora — 'Gobernadora anuncia pausa al racionamiento para abonados de Carraízo' (Sept. 1, 2026) · El Nuevo Día — September calendar for Zona 1 / Zona 2 (Aug. 31, 2026) · AAA (@AcueductosPR) on X — cistern-truck notices 'durante el plan de interrupciones programadas' (Sept. 2, 2026)
Windows above are computed from the start time and 48-hour cadence in AAA’s published plan — AAA adjusts valves around each switch and pressure returns gradually, so treat the boundary as approximate. Plan changes are AAA’s to announce: verify with your municipality’s emergency office below.
No match in AAA’s published sector lists. Sectors not listed are not in the rotation as published — browse the full lists below, or confirm with AAA at (787) 620-2482.
States are computed from AAA’s published calendar; AAA adjusts valves around each 6:00 AM switch, so treat boundaries as approximate.
Or browse the full sector lists
San Juan
Zone 1: Viejo San Juan, Miramar, Condado, Ocean Park, Hill Mansions, Park Gardens, Villa Capri, Venus Gardens, El Dorado, Urb. San Gerardo, Sector El Cinco, Villa Húcar, Camino Hogar del Niño, Ave. Winston Churchill, Ave. Paraná, PR-844, El Cerezal, Cupey Alto, PR-199, Urb. Paseos, Paseo Real, Paseo la Fuente, Paseo las Vistas 1 y 2, Paseo las Brisas, Paseo Mayor, Paseo del Prado, Paseo del Parque, Paseo San Juan, Paseo Alto, Villas del Sol, Sector El Capá, Borinquen Gardens, La Marina, Los Choferes, Cupey Gardens, Montebello, Reparto Universitario, Villa Andalucía, Ext. San Agustín, Cond. Town Park, Bo. Vista Alegre
Zone 2: PR-876, Complejos Montebello, Zona Industrial en PR-877, Ave. 65 de Infantería, PR-3, Venezuela, Buen Consejo, Experimental, Cambridge Park, Reparto Contemporáneo, Chalets de Cupey, Antigua Vía, Villas de Lomas Verdes, Antón Santi, Villa Nevárez, Centro Médico, Jardines Metropolitano, Pueblo de Río Piedras, Ave. Barbosa, Cantera, Bda. Bitumul e Israel, Floral Park, San José, Pérez Morris, Valencia, Quintana, Manuel A. Pérez y sectores aledaños, PR-3 Int. PR-181 hasta PR-3 Int. PR-849, Country Club 29, Hill Brothers, Parcelas Falú, Las Virtudes, Reparto Sevilla, Monte Hatillo, Carr. 849, Terrazas de San Juan, Colinas de San Juan, La Vista, San Martín, Sector Monteflores, Calle San Mateo, Calle Julián Pesante, Calle Del Valle, Res. Villa Kennedy, Res. Las Casas, Calle Lutz, Villa Palmera, Monte Carlo, Santo Domingo, Portal La Reina, Berwind y Monte Park
Trujillo Alto
Zone 1: Round Hill, PR-181 Int. con la PR-8860, Lago Alto, Terra Linda, Complejos San Rafael, Patio Sevillano, Villas del Lago y complejos aledaños, PR-846, Complejos Interamericana, Ciudad Universitaria, Bda. Los González, Carr. 175 desde la Int. con la PR-181 hasta Km 0.3, Villa Margarita, Lomas de Trujillo, Sunville, Urb. El Conquistador, La Lomita, Vista Serena, Riveras del Río, PR-845 desde la Int. con la PR-175, Rincón Español, Jardines Morales, Fair View, Sector El Hoyo, Parcelas Carraízo, Haciendas de Carraízo, Villas de Carraízo, Terrazas de Carraízo, PR-850, Bo. Las Cuevas, Colinas de Fair View, Villas de Caney, Andreas Court, PR-199, Los Paseos, Borinquen Gardens
Zone 2: PR-181, Complejos de Encantada, PR-181 hasta Int. PR-851, Bo. La Gloria, Bo. Dos Bocas, Sector Talanco, Quebrada Negrito, Coco Panel, Pueblo de Trujillo Alto, Bo. Masa Sabana, Wonderville y colindancia con Bo. Santa Rita (Gurabo)
Carolina
Zone 1: Isla Verde, Tanque La Loma, Carruzos I, Carr. 857 Km 5.1 hasta Int. con Carr. 185, Carr. 856 hasta Int. con Carr. 853, Bo. Barrazas, Sector Golder Valley, Carr. 853 Km 8.1–8.6, Sector Cuesta Los Flacos, Sector Cedro, Calle Monoloro, Calle Yagrumo, Calle La Rosa, Carr. 859 Km 0.4–2.6, Carr. 857 Km 1.6–4.9, Sector La Aldea, Sector Las Chispas, Carr. 857 Km 2.7–3.0, Carr. 859 Km 3.0 hasta Carr. 857 Km 2.7, Urb. Villa Retorno, Sector Los Carmonas, Tanques Gemelos, Bo. Santa Cruz, Carr. 859 Km 1.0–3.6, Sector El Trompito, Calle Aldea, Sector Los Cubas, Sector Quebrada Limones, Sector Los Nieves, Sector Los Sosas, Carruzo IV, Sector Los Lajas, Sector Los Canales, Carr. 856 Km 1.8–3.5, Carr. 856 Int. 856 hasta Km 2.0, Carr. 856 Km 2.0 hasta Carruzo V, Sector Las Filipinas, Carr. 856 hasta 500 m antes de la Int. con la Carr. 185, Sector Negro Pagán, Sector Calo I y II, Sector Cacao Centro, Sector UGT, Sector Los Rivera, Sector Las Gaviotas, Sector Los Febres, Sector Taíno, Carr. 858 Km 0.8–3.8, Aeropuerto Luis Muñoz Marín, Urb. Vista Mar, Urb. Catelana Garden, Urb. Jardines de Country Club, Sabana Bajo, Urb. Country Club, Villas Asturias, Sabana Gardens, Valle Arriba Heights, Urb. Villa Fontana, Urb. Alturas de Villa Fontana, Villa Cooperativa, Villa Venecia, Jardines de Borinquen, Villa Justicia, Urb. Rosa María, Urb. Vista Mar Marina, Urb. José Quiñones, Villa Flores, Urb. Los Ángeles, Urb. Villa Carolina
Zone 2: Carr. 853 Km 2.7–3.6, Camino Zequeira, Sector La Cantera, Bombas Arrallanes I, Sector Hoyo Frío, Sector El Tamarindo, Sector Los Benítez, Carr. 853 Km 3.6–8.0, Barrazas, Sector Los Tapias, Cuesta Los Flacos Km 1, Sector Los Brillones, Sector Los López, Sector Los Márquez, Sector Templo El Arca, Sector Los Álamos, Sector Los Fernández, Sector Aguas Claras, Carr. 853 Km 6.8 hasta Int. con la Carr. 185, Sector Los Flores, Bo. Cedros, Carr. 185 Km 11.0–12.8, Urb. Metrópolis, Apartamentos Metro Monte, Urb. Estancias Metrópolis, Chalets de Metrópolis, Urb. Carolina Alta, Condominio Paseo de Monte Flores, Urb. Lomas Alta, Residencial Lomas Alta, Residencial Roberto Clemente, Residencial Los Mirtos, Urb. Carolina Housing, Urb. Los Árboles, Condominio Villa San Antón, Sector Cuesta Quiles, Sector La Lomita, Villa Madrigal, La Alambra, Club Yaucano, Sector Mameyal, Urb. Rollings Hills, Camino Los Parceleros, Carr. 860 Km 0.2 hasta el tanque Metrópolis, Urb. Estancia del Camino, Urb. Jardines de Carolina, Parque Escorial, Escorial Plaza, Carr. 848, Bo. Saint Just, Urb. Parque Ecuestre, Torrecillas y Loíza Valley
Canóvanas
Zone 1: Sector Los Castillos, Bo. Lomas Cole, Quebrada Prieta, Carr. 785 Km 8.6–11.0, Sector La Vega, Sector Martín González I, Sector Loma de Cubuy, Lomastino, El Arca, Parcelas Las 400, PR-185 Km 14.1–12.6, Sector Las Yayas, Sector Los Sosa, Sector Los Pérez, Sector Los González, Sector Los Café, PR-186 Km 1.3–7.0, Sector Las Cuadras
Zone 2: PR-962, Bo. Cambalache, Estancias de Campo Rico, Finca Maravilla, Lomas del Viento, Parcelas Viejas y Nuevas Campo Rico, Tanque Parcelas Nuevas Campo Rico, Sector El Río después de Los Chorritos, Sector Finca Pozo, Canovanillas, Carr. 185 Km 1.6–8.6, Finca Calzada, Las Haciendas de Canóvanas, Urb. Las Haciendas, Los Navarros, Mansiones del Tesoro, PR-941, Quintas de Canóvanas, Hipódromo Camarero y Urb. Ciudad Jardín
Loíza
Zone 1: Barrio Torrecillas, Sector Piñones y Sector Latorre
All of Loíza’s affected sectors are in Zone 1.
Gurabo
Zone 1: Masas Aisladas
Zone 2: Santa Rita
Juncos
Zone 1: Sector Las Piñas
All of Juncos’s affected sectors are in Zone 1.
The published calendar — paused
None of these switches is in effect while the pause holds. The first that could take effect is Tue, Sep 22 — only if AAA resumes the rotation.
Switches would happen at 6:00 AM AST on the dates shown.
Getting through the rotation
- Before your zone’s window closes, store what you’ll need — ready.gov figures one gallon per person per day, more for children, the sick, and pets. Fill containers you can seal.
- While your sector is dry, 40 oasis and refill points are mapped below — AAA’s run 9 a.m. to 7 p.m., municipal hours vary by town. And a running leak is water nobody gets: report breaks to AAA at (787) 620-2482 or acueductospr.com.
- When service returns, run cold taps until the water comes through clear. If in doubt about quality, CDC guidance is a rolling boil for one minute before drinking.
- Afterward, watch your bill — AAA has adjusted bills for customers left without service before. Keep track of your sector’s dry days.
Municipal emergency offices (OMME)
- San Juan: (787) 480-2222
- Carolina: (787) 701-4455
- Loíza: (787) 876-6549 / (787) 876-3561
- Canóvanas: (787) 876-2465
- Trujillo Alto: (787) 760-4440
- Gurabo: (787) 737-3459
- Juncos: (787) 333-6106
Oasis — where to get water
40 refill points across 6 townsLast confirmed Aug 7 — may be out of date
This list may be out of date. Last confirmed Aug 7, 45 days ago. Oasis open and close with the rotation — call your municipality’s emergency office (OMME) before travelling to one.
All 40 refill points, by municipio
Carolina (18)
- Centro Comunal EstrellitasSabana Abajo, Carr. 190 Km. 2.3
- Centro Comunal La CerámicaUrb. Eduardo J. Saldaña, Calle Roble
- Cancha Lulo GonzálezVilla Carolina, Complejo Deportivo Roberto Clemente
- Cancha de Baloncesto barrio CacaoCarr. 858, Bo. Cacao
- Estacionamiento Parque Soccer 4ta Country ClubCalle 482, Urb. Country Club
- Parque Julia de Burgos fase IAve. Roberto Clemente
- Centro Comunal MetrópolisUrb. Metrópolis, Avenida C
- Paseo Lineal Blasina5ta Sección Villa Carolina, Calle 516
- Centro Comunal Saint JustCarr. 874 Km. 1.1, Calle Betania
- Centro Comunal Santa CruzCarr. 859, Calle Laurel
- Centro Comunal barrio CarruzosCarr. 857, Km 9.4
- Centro Zumbador (Head Start)Urb. Jardines de Country Club B
- Centro de Servicios Municipales de Isla Verde
- Centro de Servicios Municipales de Barrazas
- Plaza EscorialCalle de Diego (detrás de Sam's Club)
- Pozo EscorialAAA
- Pozo CambuteAAA
San Juan (18)
- Centro Comunal de Caimito
- Frente Esc. Rafael Quiñones Vidal
- Sector Las Curias
- PR-844 frente Esc. Especializada Rafael A. Corretjer
- PR-844 Estancias del Boulevard
- Residencial Villa Esperanza
- Urb. Venus Gardens, calle Lesbos
- Parque Victoria, Villa Corozo
- Res. Las Margaritas, Boys & Girls Club
- Res. Villa Kennedy
- Res. Las Casas
- Res. Luis Lloréns Torres — Teatro Osvaldo La Salle
- Calle Collores esquina María Isabel
- Calle Marina, Edif. 30
- Calle Marina, Edif. 7
- Pozo Las AméricasAAA
- Pozo Miguel SuchAAA
- Pozo SorbonaAAA
Caguas (1)
- Planta de Filtros Caguas NorteAAA
Dorado (1)
- Pozo Santa RosaAAA
Naguabo (1)
- Planta de Filtros Río BlancoAAA
Toa Baja (1)
- Pozo CampanillasAAA
Sources, coverage and how to read the pins
Zones 1 and 2 are sector-level within each town — this map deliberately draws no zone shapes; use the sector search above for your zone.
Sources: Municipio de San Juan — Reportalo SJ oasis map (official municipal platform) · Municipio de Carolina — “Alcalde Aponte pone en marcha red de Oasis de Agua Potable en las Comunidades” (official release) · AAA — Plan de Interrupciones Programadas, Planta de Filtros Sergio Cuevas (official plan document). Other municipios have announced oasis without published locations yet — we add sites only from official announcements; check your municipality’s channels or OMME line meanwhile. Approximate pins from OpenStreetMap data (ODbL).
Source: Autoridad de Acueductos y Alcantarillados — Plan de Interrupciones Programadas, Planta de Filtros Sergio Cuevas (official plan document) (PDF), via acueductospr.com. Transcribed 2026-08-07.
AAA, in its own words
Notices from @AcueductosPR, the utility’s official account · translated from Spanish, each linked to the original
Yesterday · Sun, Sep 20
Culmina the repair of a 2-inch pipeline outlet in the Dominguito pump station's distribution network. Drinking water distribution to customers in Dominguito and nearby communities in #Arecibo is gradually stabilized.
Culmina la reparación de un salidero reportado en tubería de 2” de diámetro en la red de distribución de la estación de bombas Dominguito. Se estabiliza paulatinamente la distribución de agua potable para clientes en Dominguito y comunidades cercanas en #Arecibo.
Sat, Sep 19
The distribution network of the Dos Millones pump station in #Arecibo continues to gradually recover from the hours of yesterday after the repair work at the power substation was completed. The gradual system restore isined for customers in Hato Arriba and is being worked to recover the service in the Dominguito area in #Arecibo, as well as in Pajuil, Las Piñas, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities. Brigades areined in the distribution networks by repairing outlets and making adjustments in the pumps to accelerate the restore to the high and distant areas of the system.
La red de distribución de la estación de bombas Dos Millones en #Arecibo continúa recuperando gradualmente desde horas de la noche de ayer luego de completadas las labores de reparación en la subestación eléctrica. Se mantiene el restablecimiento paulatino del sistema para clientes en Hato Arriba y se trabaja para recuperar el servicio en la zona de Dominguito en #Arecibo, así como también, en Pajuil, Las Piñas, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios. Brigadas se mantienen en las redes de distribución reparando salideros y realizando ajustes en los bombeos para agilizar el restablecimiento hacia las zonas altas y distantes del sistema.
As the drinking water service is fully restored, after completion of the work at the power substation at the Two Millions pump station in Arecibo, we report the availability of the oasis. As part of mitigation measures, we have assigned tank trucks to the Municipal Emergency Management Offices (#OMME) in #Arecibo and #Hatillo, in order to meet the needs of our customers. We urge subscribers to contact their respective OMME contact numbers to receive assistance.
Mientras se restablece el servicio de agua potable en su totalidad, luego de completados los trabajos en la subestación eléctrica de la estación de bombas Dos Millones en Arecibo, informamos la disponibilidad de oasis. Como parte de las medidas de mitigación, hemos asignado camiones cisterna a las Oficinas Municipales para el Manejo de Emergencias (#OMME) en #Arecibo y #Hatillo, con el fin de atender las necesidades de nuestros clientes. Exhortamos a los abonados a comunicarse con los números de contacto de su OMME correspondiente para recibir asistencia.
Personnel is mobilized for inspection of the Pozas 2 pumping station in #Ciales, after failure While the incident is working, customers in the Bo. Pozas and neighboring communities experience interruption of drinking water service.
Personal se moviliza para inspección de la estación de bombas Pozas 2 en #Ciales, luego de falla reportada Mientras se trabaja la incidencia, clientes en el Bo. Pozas y comunidades aledañas experimentan interrupción del servicio de agua potable.
Fri, Sep 18
The Talavera well is out of operation due to a reported failure in the voltage of the power grid. Event to LUMA Energy under order c7164970. While energy is stabilized, customers in PR-119 sectors, Paseo Del Sol, La Pica and neighboring communities in #Camuy experience drinking water service disruption.
El pozo Talavera se encuentra fuera de operación por falla reportada en el voltaje de la red eléctrica. Evento reportado a LUMA Energy bajo la orden c7164970. Mientras se estabiliza la energía, clientes en sectores de la PR-119, Paseo Del Sol, La Pica y comunidades aledañas en #Camuy experimentan interrupción del servicio de agua potable.
The work at the two million pumping station in Arecibo has culminated satisfactorily. The system has been powered and is being operated and distributed. The gradual restoration of drinking water service for subscribers in Hato Up, Hato Abajo, Abra San Francisco and Dominguito in Arecibo begins, as well as Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities. The recovery of drinking water service will continue for hours of the night, early morning and will be extended during the morning, Saturday, to the most distant parts of the system.
Culminan satisfactoriamente las labores en la subestación eléctrica de la estación de bombas Dos Millones en #Arecibo. El sistema fue energizado y se encuentra operando y distribuyendo. Comienza el restablecimiento gradual del servicio de agua potable para abonados en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios. La recuperación del servicio de agua potable continuará durante horas de la noche, madrugada y se extenderá durante el día de mañana, sábado, hacia las partes más lejanas del sistema.
Culmina the 12” pipeline repair in the Islote area in the Municipality of #Arecibo. Clients in Islote and neighboring communities have gradual restoration of drinking water service.
Culmina la reparación de tubería de 12” de diámetro en la zona de Islote en el Municipio de #Arecibo. Clientes en Islote y comunidades aledañas tienen restablecimiento paulatino del servicio de agua potable.
Additional tests are carried out required by LUMA Energy as part of the certification and authorization processes to power the electric substation, after replacing the damaged fuses at the Dos Millones pumping station in #Arecibo. Subscribers in Hato Up, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities experience interruption of drinking water service while the process is completed.
Se realizan pruebas adicionales requeridas por LUMA Energy como parte de los procesos de certificación y autorización para energizar la subestación eléctrica, luego de reemplazados los fusibles averiados en la estación de bombas Dos Millones en #Arecibo. Abonados en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas experimentan interrupción del servicio de agua potable, mientras se completa el proceso.
Culmina the repair of an outlet on the urban distribution network of the Municipality of #Utuado. Clients in the urban area and neighboring communities have gradual restoration of drinking water service.
Culmina la reparación de un salidero reportado en la red de distribución urbana del Municipio de #Utuado. Clientes en la zona urbana y comunidades aledañas tienen restablecimiento gradual del servicio de agua potable.
We inform you that the Buena Vista Grande Pumping Station will be out of operation due to repair work on a 10-inch line located on the PR-829 road, km 5.0. Works: Staff will be performing the repair of the line. The work will take an estimated duration of 4 hours. Impact on service: During this period, subscribers may experience low pressures or temporary interruption of drinking water service. Affected sectors: PR-829, Sabana Parcelas, Los Barros, Guaraguao Up and adjacent areas.
Informamos que la Estación de Bombas Buena Vista Grande estará fuera de operación debido a trabajos de reparación de una línea de 10 pulgadas, ubicada en la carretera PR-829, km 5.0. Trabajos: Personal estará realizando la reparación de la línea. Los trabajos tendrán una duración estimada de 4 horas. Impacto en el servicio: Durante este periodo, los abonados podrían experimentar bajas presiones o interrupción temporera del servicio de agua potable. Sectores afectados: Carretera PR-829, Parcelas Sabana, Los Barros, Guaraguao Arriba y áreas adyacentes.
Brigada works the repair of an outlet in the urban distribution network of the Municipality of #Utuado. Clients in the urban area and neighboring communities will experience interruption of drinking water service, while the tasks are completed.
Brigada trabaja la reparación de un salidero reportado en la red de distribución urbana del Municipio de #Utuado. Clientes en la zona urbana y comunidades aledañas experimentarán interrupción del servicio de agua potable, mientras se completan las labores.
The bombing of the El Maestro tank towards Zanjas and Yeguada in the municipality of #Camuy resumed operation. Subscribers in Yeguada, Membrillo, Camino Las Flores, Abra Honda, Bridge, Zanjas, PR-486 and neighboring communities will have gradual restoration of drinking water service during today's day, Friday.
Los bombeos del tanque El Maestro hacia Zanjas y Yeguada en el Municipio de #Camuy reanudaron operación. Abonados en Yeguada, Membrillo, Camino Las Flores, Abra Honda, Puente, Zanjas, PR-486 y comunidades aledañas tendrán restablecimiento paulatino del servicio de agua potable durante el día de hoy, viernes.
For Friday, 18 September, the installation of a flow meter is coordinated in the Algarrobo well of the Municipality of #VegaBaja. The work will begin at 8:00am and will extend for a period of 4 hours, so that customers in Algarrobo, Eye of Water, Colombo, Miss Kelly, Camino del Sol and neighboring communities could experience interruption of drinking water service, while the incident is working.
Para el viernes, 18 de septiembre, se coordina la instalación de un metro de flujo en el pozo Algarrobo del Municipio de #VegaBaja. Las labores iniciarán a las 8:00am y se extenderán por un período de 4 horas, por lo que clientes en Algarrobo, Ojo de Agua, Colombo, Miss Kelly, Camino del Sol y comunidades aledañas podrían experimentar interrupción del servicio de agua potable, mientras se trabaja la incidencia. Estas labores tienen como propósito mejorar la operación del pozo para beneficio de los abonados.
The work of replacement of fusibles at the Dos Millones pump station in #Arecibo was completed during the afternoon of yesterday, Thursday. Certifications are being processed and corresponding authorizations are expected by LUMA Energy to power the power substation. Subscribers in Hato Up, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and surrounding communities experience drinking water service disruption while the process is completed.
Los trabajos de reemplazo de fusibles en la estación de bombas Dos Millones en #Arecibo fueron completados durante la tarde de ayer, jueves. Se tramitan las certificaciones y se espera por las autorizaciones correspondientes por parte de LUMA Energy para energizar la subestación eléctrica. Abonados en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas experimentan interrupción del servicio de agua potable, mientras se completa el proceso.
Thu, Sep 17
In addition, the residential residence of Manuel Zeno Gandía, in Arecibo, has been repaired.Controlled drainage is carried out in the network to speed up the recovery of the service. Subscribers in this community and neighboring sectors will have gradual restoration of drinking water service during the night hours.
Culmina la reparación del salidero reportado en la red de distribución del Residencial Manuel Zeno Gandía en #Arecibo. Se realizan desagües controlados en la red para agilizar la recuperación del servicio. Abonados en esta comunidad y sectores aledaños tendrán restablecimiento gradual del servicio de agua potable durante horas de la noche.
For Wednesday, September 23, the redundancy pump installation will be coordinated at the Achiotes 2 pump station in the municipality of #Naranjito. These works are beneficial to customers as they provide an alternate distribution system in case of future failures in the pumping. Improvements will start at 7:00am and will be extended for a period of 10 hours. Clients in Las Jaguas, Fondo del Saco, El Peñon, Espinel, El Cuco, Achiote and neighbouring communities in this municipality will experience interruption of drinking water service. Once the works are completed, pumping operation will be resumed, so the stabilization of drinking water service is estimated from afternoon hours and night hours. Drinking water in cisterns will be coordinated as a mitigation measure.
Para el miércoles, 23 de septiembre, se coordina la instalación de bomba de redundancia en la estación de bombas Achiotes 2 en el Municipio de #Naranjito. Estos trabajos son de beneficio para los clientes ya que proveen un sistema alterno de distribución en caso de futuras fallas en el bombeo. Las mejoras iniciarán a las 7:00am y se extenderán por un período de 10 horas. Clientes en Las Jaguas, Fondo del Saco, El Peñon, Espinel, El Cuco, Achiote y comunidades aledañas en este municipio experimentarán interrupción del servicio de agua potable. Una vez completados los trabajos, se reanudará la operación del bombeo, por lo que se estima la estabilización del servicio de agua potable a partir de horas de la tarde y noche. Se coordinará el acarreo de agua potable en camiones cisterna, como medida de mitigación.
The Two Millions pumping station in #Arecibo continues to be out of operation. Staff are inspecting the electrical systems and verifying the integrity of the pumping system. Subsequently, the damaged fusibles will be installed in the AAA substation that energizes the system. Subscribers in Hato Up, Hato Down, Abra San Francisco and Dominguito in #Arecibo, as well as, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities experience temporary interruption of drinking water service while the system is energized.
La estación de bombas Dos Millones en #Arecibo continúa fuera de operación. Personal se encuentra inspeccionando los sistemas eléctricos y verificando la integridad del sistema de bombeo. Posteriormente, se procederá con la instalación de los fusibles averiados en la subestación de la AAA que energiza al sistema. Abonados en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas experimentan interrupción temporal del servicio de agua potable, mientras se energiza el sistema.
We inform that the situation at the Cubuy Filter Plant in the municipality of #Canóvanas, was addressed. Operational status: The pumps are operating normally and the plant continues its operation. The system is in the recovery process, so the drinking water service will be gradually restored in the affected sectors.
Informamos que la situación reportada en la Planta de Filtros Cubuy en el municipio de #Canóvanas, fue atendida. Estatus operacional: Las bombas se encuentran operando con normalidad y la planta continúa su operación. El sistema se encuentra en proceso de recuperación, por lo que el servicio de agua potable se restablecerá paulatinamente en los sectores afectados.
We inform that the work to remove the obstruction in the dam that supplies the Guzmán Upper Filter Plant, located in #RíoGrande, culminated. Operational status: The pumps are operating normally and the entry of raw water to the plant has been restored. Service recovery: The system is in the recovery process. Subscribers from the Hoyo, Maga, Medina, Palmasola and adjacent areas will begin to experience the gradual restoration of the drinking water service.
Informamos que culminaron las labores para remover la obstrucción en la represa que suple a la Planta de Filtros Guzmán Arriba, ubicada en #RíoGrande. Estatus operacional: Las bombas se encuentran operando con normalidad y se restableció la entrada de aguas crudas a la planta. Recuperación del servicio: El sistema se encuentra en proceso de recuperación. Los abonados de los sectores Hoyo, Maga, Medina, Palmasola y áreas adyacentes comenzarán a experimentar el restablecimiento paulatino del servicio de agua potable.
Reported to Luma Energy with the order c7157247. Subscribers in Hato Up, Hato Down, Abra San Francisco and Dominguito in #Arecibo, as well as, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities experience temporary interruption of drinking water service, while stabilizing energy.
La estación de bombas Dos Millones en #Arecibo se encuentra fuera de operación por falla reportada en el sistema eléctrico. Reportado a Luma Energy con la orden c7157247. Abonados en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas experimentan interrupción temporal del servicio de agua potable, mientras estabiliza la energía.
We inform you that the Cubuy Filter Plant (PF Cubuy), in the municipality of #Canóvanas, is stopped because the raw water intake is blocked. Operational status: Our staff are performing work to clear the intake and restore the raw water entry to the plant as soon as possible. Impact on the service: Our subscribers supported by this system could experience low pressures or temporary interruption of the drinking water service in sectors of Canóvanas and adjacent areas.
Informamos que la Planta de Filtros Cubuy (PF Cubuy), en el municipio de #Canóvanas, se encuentra detenida debido a que la toma de aguas crudas está tapada. Estatus operacional: Nuestro personal se encuentra realizando labores para despejar la toma y restablecer la entrada de aguas crudas a la planta a la mayor brevedad posible. Impacto en el servicio: Nuestros abonados suplidos por este sistema podrían experimentar bajas presiones o interrupción temporera del servicio de agua potable en sectores de Canóvanas y áreas adyacentes.
Wed, Sep 16
The Two Millions bombing station in #Arecibo is out of operation. System inspection is coordinated to resume distribution. Subscribers in Hato Up, Hato Down, Abra San Francisco and Dominguito in #Arecibo, as well as, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities experience temporary interruption of drinking water service, while the incident is served.
La estación de bombas Dos Millones en #Arecibo se encuentra fuera de operación. Se coordina la inspección del sistema para reanudar la distribución. Abonados en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas experimentan interrupción temporal del servicio de agua potable, mientras se atiende la incidencia.
We inform you that the Guzmán Upper Filter Plant, located in #RíoGrande, is out of operation due to the dam blocked by the rains recorded in the area, which has affected the entry of raw water to the facility. Operational status: Our operational staff are performing work to remove the blockage in the dam and restore the entry of raw water, in order to resume the production of drinking water as soon as possible. Impact on the service: Subscribers in the sectors of: Hoyo Maga Medina Palmasola Neighboring areas in the municipality of #RioGrande may experience low pressures or temporary interruption of the drinking water service while the operation of the plant is normalized.
Informamos que la Planta de Filtros Guzmán Arriba, ubicada en #RíoGrande, se encuentra fuera de operación debido a la represa obstruida por las lluvias registradas en el área, lo que ha afectado la entrada de aguas crudas a la instalación. Estatus operacional: Nuestro personal operacional se encuentra realizando labores para remover la obstrucción en la represa y restablecer la entrada de aguas crudas, con el fin de reanudar la producción de agua potable a la mayor brevedad posible. Impacto en el servicio: Los abonados en los sectores de: Hoyo Maga Medina Palmasola Áreas adyacentes en el municipio de #RioGrande podrían experimentar bajas presiones o interrupción temporera del servicio de agua potable mientras se normaliza la operación de la planta.
We report that the repair work of the damaged pipeline culminated at the exit of the Cubuy Filter Plant to the Las 400 sector. Operational status: The work was completed and the system is in the process of recovery. Drinking water service: Service will be gradually restored in the affected sectors as the system stabilizes.
Informamos que culminaron los trabajos de reparación de la tubería averiada en la salida de la Planta de Filtros Cubuy hacia el sector Las 400. Estatus operacional: Los trabajos fueron completados y el sistema se encuentra en proceso de recuperación. Servicio de agua potable: El servicio se restablecerá de manera gradual en los sectores afectados conforme se estabilice el sistema.
We inform you that repairs of a damaged pipeline will be carried out at the exit of the Cubuy Filter Plant to the Las 400 sector. Operational status: AAA personnel are mobilized to the area to carry out the corresponding repairs. Impact on service: Subscribers from the sectors served by this line could experience low pressures or temporary interruptions in the drinking water service while the works are completed.
Informamos que se estarán realizando trabajos de reparación de una tubería averiada en la salida de la Planta de Filtros Cubuy hacia el sector Las 400. Estatus operacional: Personal de la AAA se moviliza hacia el área para realizar los trabajos de reparación correspondientes. Impacto en el servicio: Los abonados de los sectores servidos por esta línea podrían experimentar bajas presiones o interrupciones temporeras en el servicio de agua potable mientras se completan los trabajos.
Today, Wednesday, 16 September, work will be carried out on the relocation of flow meter and pipeline connections in the Manatí well system 1. The work aims to improve the operation of the well and optimize the drinking water service to customers in #Manatí communities. The work will begin at 8:00am and will extend for a period of 8 hours. Clients in the city centre of #Manatí and neighboring communities will experience interruption of drinking water service. It is estimated that the drinking water service will be restored from afternoon hours, if no inconveniences arise with the work.
Hoy miércoles, 16 de septiembre, se realizarán trabajos de relocalización de metro de flujo y conexiones de tubería en el sistema del pozo Manatí 1. Las labores tienen como propósito mejorar la operación del pozo y optimizar el servicio de agua potable a clientes en comunidades de #Manatí. Los trabajos iniciarán a las 8:00am y se extenderán por un período de 8 horas. Clientes en el casco urbano de #Manatí y comunidades aledañas experimentarán interrupción del servicio de agua potable. Se estima el restablecimiento del servicio de agua potable a partir de horas de la tarde, de no surgir inconvenientes con las labores.
Tue, Sep 15
The excavation is underway and the controlled opening of the distribution system is carried out to gradually increase the levels of the Two Millones tank. Also, controlled drainage is carried out through the network to speed up recovery. The restoration of drinking water service for customers in the urban area, PR-2, Hato Up, Los Caños, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as the PR-2, urban area, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities will begin from the morning hours. The restoration of the service will extend during tomorrow, Wednesday, to the highest parts of the municipalities and to coordinate the water recovery system, as the normal efforts are measured.
Culminan las labores de reparación de salidero en la red que suple a la estación de bombas Dos Millones en #Arecibo. Se procede a cubrir la excavación y a realizar la apertura controlada del sistema de distribución para aumentar gradualmente los niveles del tanque Dos Millones. Asimismo, se realizan desagües controlados a través de la red para agilizar la recuperación. El restablecimiento del servicio de agua potable para clientes en la zona urbana, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, la PR-2, zona urbana, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios comenzará a partir de horas de la madrugada. El restablecimiento del servicio se extenderá durante el día de mañana, miércoles, hacia las partes más altas y lejanas del sistema en ambos municipios. Como medida de mitigación y apoyo a los esfuerzos de recuperación, se coordinará para mañana el acarreo de agua potable en camiones cisterna, mientras se normaliza el servicio.
The excavation is underway and the controlled opening of the distribution system is carried out to gradually increase the levels of the Two Millones tank. Also, controlled drainage is carried out through the network to speed up recovery. The restoration of drinking water service for customers in the urban area, PR-2, Hato Up, Los Caños, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as the PR-2, urban area, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities will begin from the morning hours. The restoration of the service will extend during tomorrow, Thursday, to the highest parts of the municipalities and to the milk in the system, as the water recovery efforts are coordinated.
Culminan las labores de reparación de salidero en la red que suple a la estación de bombas Dos Millones en #Arecibo. Se procede a cubrir la excavación y a realizar la apertura controlada del sistema de distribución para aumentar gradualmente los niveles del tanque Dos Millones. Asimismo, se realizan desagües controlados a través de la red para agilizar la recuperación. El restablecimiento del servicio de agua potable para clientes en la zona urbana, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, la PR-2, zona urbana, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios comenzará a partir de horas de la madrugada. El restablecimiento del servicio se extenderá durante el día de mañana, jueves, hacia las partes más altas y lejanas del sistema en ambos municipios. Como medida de mitigación y apoyo a los esfuerzos de recuperación, se coordinará para mañana el acarreo de agua potable en camiones cisterna, mientras se normaliza el servicio.
The repair work of the trawling field outlet identified in the network that supplies to the Dos Millones pumping station in #Arecibo continues. Staff completed the cut of the damaged section. It proceeds with the preparation of the existing pipeline to insert the pieces and the new tube section. Clients in the urban area, PR-2, Hato Up, Los Caños, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as the PR-2, urban area, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities experience interruption of drinking water service, while continuing work.
Continúan las labores de reparación de salidero campo traviesa identificado en la red que suple a la estación de bombas Dos Millones en #Arecibo. Personal completó el corte del tramo averiado. Se procede con la preparación de la tubería existente para insertar las piezas y el nuevo tramo de tubo. Clientes en la zona urbana, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, la PR-2, zona urbana, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios experimentan interrupción del servicio de agua potable, mientras continúan las labores.
Continues the repair work of the trawling field outlet identified in the network that supplies to the Dos Millones pump station in #Arecibo. Staff works the cutting of the pipeline to replace the damaged section of the distribution line of 12”. Clients in the urban area, PR-2, Hato Up, Los Caños, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as the PR-2, urban area, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighbouring communities in both municipalities experience interruption of drinking water service, while the work continues.
Continúan las labores de reparación de salidero campo traviesa identificado en la red que suple a la estación de bombas Dos Millones en #Arecibo. Personal trabaja el corte de la tubería para reemplazar el tramo averiado de la línea de distribución de 12”. Clientes en la zona urbana, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, la PR-2, zona urbana, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios experimentan interrupción del servicio de agua potable, mientras continúan las labores.
Clients in the urban area, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as the PR-2, urban area, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities experience interruption of drinking water service, while continuing the work.
Continúan las labores de reparación de salidero campo traviesa identificado en la red que suple a la estación de bombas Dos Millones en #Arecibo. Clientes en la zona urbana, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, la PR-2, zona urbana, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios experimentan interrupción del servicio de agua potable, mientras continúan las labores.
We inform you that it was necessary to close the system to perform repairs for a breakdown on a distribution line in the Peniel community, in the municipality of #RíoGrande. Staff are working to complete the repair and restore the service as soon as possible. During the works, subscribers in the area may experience low pressures or disruptions in the drinking water service.
Informamos que fue necesario cerrar el sistema para realizar trabajos de reparación de una avería en una línea de distribución en la comunidad Peniel, en el municipio de #RíoGrande. Personal se encuentra trabajando para completar la reparación y restablecer el servicio a la mayor brevedad posible. Durante los trabajos, los abonados del área podrían experimentar bajas presiones o interrupciones en el servicio de agua potable.
The work continues on the repair of the outlet field traves on the network that supplies to the bomb station Two Millones in #Arecibo. Brigades of the operational area are working on the incident. Clients in the urban area, PR-2, Hato Up, Los Caños, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as the PR-2, urban area, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities experience interruption of drinking water service, while the work continues.
Continúan las labores de reparación de salidero campo traviesa en la red que suple a la estación de bombas Dos Millones en #Arecibo. Brigadas del área operacional se encuentran trabajando la incidencia. Clientes en la zona urbana, PR-2, Hato Arriba, Los Caños, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, la PR-2, zona urbana, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios experimentan interrupción del servicio de agua potable, mientras continúan las labores.
Customers in Hato Arriba, Hato Abajo, Abra San Francisco and Dominguito in #Arecibo, as well as also, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista in #Hatillo and neighboring communities in both municipalities experience drinking water service disruption while the incident is addressed.
Personal inspecciona el sistema y la red de la estación de bombas Dos Millones en #Arecibo luego de falla identificada en los niveles de distribución. Clientes en Hato Arriba, Hato Abajo, Abra San Francisco y Dominguito en #Arecibo, así como también, Pajuil, Las Piñas, Carrizales, Campo Alegre, Buena Vista en #Hatillo y comunidades aledañas en ambos municipios experimentan interrupción del servicio de agua potable, mientras se atiende la incidencia.
Mon, Sep 14
Due to a power failure in the #Corozal area, the Black Filter Plant is out of operation. Subscribers in Negros, Parcelas Medina, Hoya Fría, Cabeza de Vaca, PR-805, Palmarejo, Palmarito, Cuchillas, Palos Blancos, Goveo, Las Cruces, Padilla Hermita, PR-647, Dos Bocas; Lomas Valley, Cuchillas and Casaba in #Naranjito, Cienegueta in #VegaAlta and neighboring communities experience drinking water service disruption. The system is monitored to resume operation once electricity is stabilized.
Debido a falla reportada en el servicio eléctrico en la zona de #Corozal, la planta de filtros Negros se encuentra fuera de operación. Abonados en Negros, Parcelas Medina, Hoya Fría, Cabeza de Vaca, PR-805, Palmarejo, Palmarito, Cuchillas, Palos Blancos, Goveo, Las Cruces, Padilla Hermita, PR-647, Dos Bocas; Lomas Valle, Cuchillas y Casaba en #Naranjito, Cienegueta en #VegaAlta y comunidades aledañas experimentan interrupción del servicio de agua potable. Se monitorea el sistema para reanudar la operación, una vez estabilizada la energía eléctrica.
The 6” line outlet repair work in the 111th branch, in front of the To-Go garage, in the #Lares Municipality, culminated satisfactorily. Controlled system opening is underway to start the recovery and operation of the Lares Urbana filter plant. Clients in the City Hall, Callejones, Piletas and nearby communities in #Lares will have gradual restoration of drinking water service during night hours and, towards the most distant parts of the system, from dawn.
Los trabajos de reparación de salidero en línea de 6” de diámetro reportado en el ramal 111, frente al garaje To-Go, en el Municipio de #Lares, culminaron de manera satisfactoria. Se procede con la apertura controlada del sistema para iniciar la recuperación y la operación de la planta de filtros Lares Urbana. Clientes en el Casco Urbano, Callejones, Piletas y comunidades cercanas en #Lares tendrán restablecimiento gradual del servicio de agua potable durante horas de la noche y, hacia las partes mas lejanas del sistema, a partir de la madrugada.
We inform you that the Pipeline Filter Plant is out of operation due to the limited extraction of raw water in the dam that supports the installation. Operational status: Our operational staffins continuous monitoring of the capture conditions and makes the necessary adjustments to optimize the production of drinking water within the current conditions. Impact on service: As a result of this condition, subscribers from the municipalities of #Canóvanas and #Loíza could experience low pressures or temporary interruptions in the drinking water service as the plant recovers level in their distribution tank.
Informamos que la Planta de Filtros Canóvanas se encuentra fuera de operación debido a la limitada extracción de aguas crudas en la represa que suple la instalación. Estatus operacional: Nuestro personal operacional mantiene un monitoreo continuo de las condiciones de captación y realiza los ajustes necesarios para optimizar la producción de agua potable dentro de las condiciones actuales. Impacto en el servicio: Como resultado de esta condición, los abonados de los municipios de #Canóvanas y #Loíza podrían experimentar bajas presiones o interrupciones temporeras en el servicio de agua potable mientras la planta recupera nivel en su tanque de distribución.
Customers in #Hatillo and #Camuy sectors in Aibonito, Quebrada, Bayaney, Echegaray and neighboring communities in both municipalities will have gradual restoration of drinking water service during the afternoon and evening of today, Monday.
Se reanuda la operación de la planta de filtros Quebrada luego de evento de turbidez en la represa. Clientes en sectores de #Hatillo y #Camuy en Aibonito, Quebrada, Bayaney, Echegaray y comunidades aledañas en ambos municipios tendrán restablecimiento paulatino del servicio de agua potable durante la tarde y noche de hoy, lunes.
The 6” line outlet repair work in the 111th branch, in front of the To-Go garage, in the municipality of #Lares, continues. Clients in the City Hall, Callejones, Piletas and nearby communities in #Lares experience drinking water service disruption as the work is completed.
Los trabajos de reparación de salidero en línea de 6” de diámetro reportado en el ramal 111, frente al garaje To-Go, en el Municipio de #Lares, continúan. Clientes en el Casco Urbano, Callejones, Piletas y comunidades cercanas en #Lares experimentan interrupción del servicio de agua potable, mientras se completan los trabajos.
Guaynabo Filter Plant We report that the work at the Santa Rosa Represa has culminated successfully. Operational status: The system is in the recovery process and the Guaynabo Filter Plant continues to recover its operational levels. Sectors that could continue to experience low pressures or temporary interruptions: Muñoz Rivera, Ave. Esmeralda, Parkville, Ave. Lopategui, high parts of Las Lomas, urban area of Guaynabo, López Cases and Canta Gallo neighborhoods; in addition to Tintillo, Buen Samaritano street, Juan Domingo, La Morenita and adjacent areas. The drinking water service will be gradually restored as the system continues to recover its operational levels.
Planta de Filtros Guaynabo Informamos que los trabajos realizados en la Represa Santa Rosa culminaron exitosamente. Estatus operacional: El sistema se encuentra en proceso de recuperación y la Planta de Filtros Guaynabo continúa recuperando sus niveles operacionales. Sectores que podrían continuar experimentando bajas presiones o interrupciones temporeras: Muñoz Rivera, Ave. Esmeralda, Parkville, Ave. Lopategui, partes altas de Las Lomas, zona urbana de Guaynabo, barrios López Cases y Canta Gallo; además de Tintillo, calle Buen Samaritano, Juan Domingo, La Morenita y áreas adyacentes. El servicio de agua potable se irá restableciendo de manera paulatina a medida que el sistema continúe recuperando sus niveles operacionales.
Guaynabo Filter Plant We inform that the repair work on one of the Santa Rosa Represa extraction pumps, which affected the capture of raw water to the Guaynabo Filter Plant, was completed. Operational status: The plant is operating and the system is in the recovery process, while operational adjustments are being made to normalize the production and distribution of drinking water. Service impact: During the recovery process, some subscribers may experience low pressures.
Planta de Filtros Guaynabo Informamos que fueron completados los trabajos de reparación en una de las bombas de extracción de la Represa Santa Rosa, que afectaba la captación de aguas crudas hacia la Planta de Filtros Guaynabo. Estatus operacional: La planta se encuentra operando y el sistema está en proceso de recuperación, mientras se realizan los ajustes operacionales necesarios para normalizar la producción y distribución de agua potable. Impacto en el servicio: Durante el proceso de recuperación, algunos abonados podrían experimentar bajas presiones. El servicio se restablecerá de manera paulatina en las comunidades servidas por este sistema.
We inform you that next Monday, September 21, 2026, #RegionMetro staff will perform work for the replacement of the filter output valve at the Barrio Nuevo Filters Plant in the municipality of #Bayamón. Duration of the work: The work will last approximately 10 hours. Impact on the service: During this period, subscribers could experience low pressure or interruption of drinking water service. Sectors that could be affected: High parts of the Algarín sector, Los Morales sector, Parcelas Barrio Nuevo and part of the Dajao neighborhood. Once the work is completed, the system will start its recovery process gradually.
Trabajos programados Informamos que el próximo lunes, 21 de septiembre de 2026, personal de la #RegiónMetro realizará trabajos para el reemplazo de la válvula de salida de los filtros en la Planta de Filtros Barrio Nuevo, en el municipio de #Bayamón. Duración de los trabajos: Las labores tendrán una duración aproximada de 10 horas. Impacto en el servicio: Durante este periodo, los abonados podrían experimentar bajas presiones o interrupción del servicio de agua potable. Sectores que podrían verse afectados: Partes altas del sector Algarín, sector Los Morales, Parcelas Barrio Nuevo y parte del barrio Dajao. Una vez finalicen los trabajos, el sistema iniciará su proceso de recuperación de manera paulatina.
We followed the drought conditions in Puerto Rico during the drought committee meeting. The rains recorded this week have contributed to a slight increase in the levels of Carraízo, La Plata and other embankments. We follow the weather conditions and the behavior of our embankments to take the necessary measures and ensure the water supply to our people.
Dimos seguimiento a las condiciones de sequía en #PuertoRico durante la reunión del Comité de Sequía. Las lluvias registradas esta semana han contribuido a un leve aumento en los niveles de Carraízo, La Plata y otros embalses. Seguimos atentos a las condiciones del tiempo y al comportamiento de nuestros embalses para tomar las medidas necesarias y asegurar el abasto de agua a nuestra gente.
We inform you that the work at the Camarones Grande Pump Station (EB) in the municipality of #Guaynabo has been completed. The station is again in operation and the system is in the process of recovery. The drinking water service will gradually be restored in the affected sectors. We thank our subscribers for their understanding during the period of the work.
Informamos que los trabajos realizados en la Estación de Bombas (EB) Camarones Grande, en el municipio de #Guaynabo, fueron completados. La estación se encuentra nuevamente en operación y el sistema está en proceso de recuperación. El servicio de agua potable se restablecerá paulatinamente en los sectores afectados. Agradecemos la comprensión de nuestros abonados durante el periodo de los trabajos.
Due to a 6” line outlet in the 111, in front of the To-Go garage, the Lares Urbana filter plant is out of operation. Customers in the City Hall, Callejones, Piletas and nearby communities in #Lares experience drinking water service disruption while repairs are underway.
Debido a salidero en línea de 6” de diámetro reportado en el ramal 111, frente al garaje To-Go, la planta de filtros Lares Urbana se encuentra fuera de operación. Clientes en el Casco Urbano, Callejones, Piletas y comunidades cercanas en #Lares experimentan interrupción del servicio de agua potable, mientras se trabaja la reparación.
The Piletas pump station in #Lares resumed operation after repair of a 6” outlet of diameter on the network. subscribers in Piletas, Callejones and surrounding communities will have gradual restoration of drinking water service during the morning and afternoon of today, Monday.
La estación de bombas Piletas en #Lares reanudó operación luego de reparación de salidero de 6” de diámetro reportado en la red. Abonados en Piletas, Callejones y comunidades aledañas tendrán restablecimiento gradual del servicio de agua potable durante la mañana y tarde de hoy, lunes.
The La Cuarta pumping station in #Ciales is out of operation due to a failure in the electricity service. LUMA Energy event c7145152. Subscribers in Pesas and surrounding communities experience drinking water service disruption while energy is restored.
La estación de bombas La Cuarta en #Ciales se encuentra fuera de operación debido a falla reportada en el servicio eléctrico. Evento de LUMA Energy c7145152. Abonados en Pesas y comunidades aledañas experimentan interrupción del servicio de agua potable, mientras se restablece la energía.
We inform you that the Bomb Station (EB) Camarones Grande, in the municipality of #Guaynabo, is out of operation due to work carried out by staff specialized in the automatic power transfer system. Estimated time: 3 hours. During this period, subscribers who use this system could experience low pressures or temporary interruptions in the drinking water service.
Informamos que la Estación de Bombas (EB) Camarones Grande, en el municipio de #Guaynabo, se encuentra fuera de operación debido a trabajos que realiza personal especializado en el sistema de transferencia automática de energía eléctrica. ⏱ Tiempo estimado: 3 horas. Durante este periodo, los abonados que se sirven de este sistema podrían experimentar bajas presiones o interrupciones temporeras en el servicio de agua potable.
Sun, Sep 13
The Morovis Urbana filter plant is out of operation due to turbidity event in the dam due to recorded rains. Subscribers in the city centre, Fránquez, Torrecillas and neighboring communities in #Morovis experience disruption of drinking water service, while stabilizing production.
La planta de filtros Morovis Urbana se encuentra fuera de operación debido a evento de turbidez en la represa por las lluvias registradas. Abonados en el casco urbano, Fránquez, Torrecillas y comunidades aledañas en #Morovis experimentan interrupción del servicio de agua potable, mientras estabiliza la producción.
Staff work to stabilize the operation of the Quebrada filter plant due to turbidity event in the dam due to recorded rains. Customers in #Hatillo and #Camuy sectors in Aibonito, Quebrada, Bayaney, Echegaray and surrounding communities could experience drinking water service disruption while production is resumed.
Personal trabaja para estabilizar la operación de la planta de filtros Quebrada debido a evento de turbidez en la represa por las lluvias registradas. Clientes en sectores de #Hatillo y #Camuy en Aibonito, Quebrada, Bayaney, Echegaray y comunidades aledañas podrían experimentan interrupción del servicio de agua potable, mientras se reanuda la producción.
We inform you that the repair works of the outlet on the street Santa Bibiana, Urb. Sagrado Corazón, in the municipality of #SanJuan culminated. Operational status: The system is in the process of recovery and our staff continues to monitor the network. Recovery of the service: Urb. Subscribers Sagrado Corazón, Cupey and surrounding areas will experience the recovery of the service gradually, as the pressures normalize.
Informamos que culminaron los trabajos de reparación del salidero en la calle Santa Bibiana, Urb. Sagrado Corazón, en el municipio de #SanJuan. Estatus operacional: El sistema se encuentra en proceso de recuperación y nuestro personal continúa monitoreando la red. Recuperación del servicio: Los abonados de Urb. Sagrado Corazón, Cupey y áreas aledañas experimentarán la recuperación del servicio de manera paulatina, conforme se normalicen las presiones.
Subscribers in Piletas, Callejones and neighboring communities experience interruption of drinking water service, while repair works are coordinated.
La estación de bombas Piletas en #Lares se encuentra fuera de operación por salidero reportado en la red. Abonados en Piletas, Callejones y comunidades aledañas experimentan interrupción del servicio de agua potable, mientras se coordinan los trabajos de reparación.
Sat, Sep 12
The Zanjas Nova and Yeguada pump stations in #Camuy will go out of operation with the purpose of increasing the distribution levels on the El Maestro tank. Subscribers in Abra Honda, Membrillo, Yeguada, Camino Las Flores and surrounding communities could experience low pressures and interruption of drinking water service during hours of the night. It is working with the repair of a damaged pump which will allow a greater distribution capacity in the benefit of customers. Restoration estimated for the morning of Sunday, September 13.
Las estaciones de bombas Zanjas Nueva y Yeguada en #Camuy saldrán de operación con el propósito de aumentar los niveles de distribución en el tanque El Maestro. Abonados en Abra Honda, Membrillo, Yeguada, Camino Las Flores y comunidades aledañas podrían experimentar bajas presiones e interrupción del servicio de agua potable durante horas de la noche. Se trabaja con la reparación de una bomba averiada la cual permitirá una mayor capacidad de distribución en beneficio de los clientes. Restablecimiento estimado para la mañana del domingo, 13 de septiembre.
The Black Filter Plant is operating and distributing after failure in the area’s electricity service in #Corozal. Subscribed in Negros, Parcelas Medina, Hoya Fría, Cabeza de Vaca, PR-805, Palmarejo, Palmarito, Cuchillas, Palos Blancos, Goveo, Las Cruces, Padilla Hermita, PR-647, Dos Bocas; Lomas Valle, Cuchillas and Casaba in #Naranjito, Cienegueta in #VegaAlta and surrounding communities will have gradual restoration of drinking water service during hours of the night and dawn, as the system recovers and optimize the pressures.
La planta de filtros Negros se encuentra operando y distribuyendo luego de falla en el servicio eléctrico de la zona en #Corozal. Abonados en Negros, Parcelas Medina, Hoya Fría, Cabeza de Vaca, PR-805, Palmarejo, Palmarito, Cuchillas, Palos Blancos, Goveo, Las Cruces, Padilla Hermita, PR-647, Dos Bocas; Lomas Valle, Cuchillas y Casaba en #Naranjito, Cienegueta en #VegaAlta y comunidades aledañas tendrán restablecimiento gradual del servicio de agua potable durante horas de la noche y madrugada, a medida que recupere el sistema y optimicen las presiones.
The pump stations Zanjas Nueva and El Maestro Yeguada in #Camuy resumed operation. Subscribers in Abra Honda, Membrillo, Yeguada, Camino Las Flores and surrounding communities have gradual restoration of drinking water service.
Las estaciones de bombas Zanjas Nueva y El Maestro Yeguada en #Camuy reanudaron operación. Abonados en Abra Honda, Membrillo, Yeguada, Camino Las Flores y comunidades aledañas tienen restablecimiento gradual del servicio de agua potable.
Fri, Sep 11
The Zanjas Nova and Yeguada pump stations in #Camuy will go out of operation with the purpose of increasing the distribution levels on the El Maestro tank. Subscribers in Abra Honda, Membrillo, Yeguada, Camino Las Flores and surrounding communities could experience low pressures and interruption of drinking water service during hours of the night. It is working with the repair of a damaged pump which will allow a greater distribution capacity in benefit of customers. Restoration estimated for the morning of Saturday, September 12.
Las estaciones de bombas Zanjas Nueva y Yeguada en #Camuy saldrán de operación con el propósito de aumentar los niveles de distribución en el tanque El Maestro. Abonados en Abra Honda, Membrillo, Yeguada, Camino Las Flores y comunidades aledañas podrían experimentar bajas presiones e interrupción del servicio de agua potable durante horas de la noche. Se trabaja con la reparación de una bomba averiada la cual permitirá una mayor capacidad de distribución en beneficio de los clientes. Restablecimiento estimado para la mañana del sábado, 12 de septiembre.
The Buena Vista pumping station is out of operation due to a failure in the power grid that energizes the pumping. Luma Energy event c7131158. Subscribers at the Bo. Buena Vista and surrounding areas in #Hatillo experience drinking water service disruption.
La estación de bombas Buena Vista se encuentra fuera de operación debido a falla en la red eléctrica que energiza al bombeo. Evento de Luma Energy c7131158. Abonados en el Bo. Buena Vista y zonas aledañas en #Hatillo experimentan interrupción del servicio de agua potable.
Our teams have completed the repair work of an outlet in #Cidra. Our brigades continue to work to reduce water losses and make the most of the available resources. #YoSirvoAPR...
Salidero REPARADO! Nuestros equipos completaron los trabajos de reparación de un salidero en #Cidra. Nuestras brigadas continúan trabajando para reducir las pérdidas de agua y aprovechar al máximo el recurso disponible. #YoSirvoAPR…
60 notices · 10 days · older posts on @AcueductosPR
No notices of that kind in the last 60.
Times are AST. Machine-translated; the Spanish original is the record. "Out now" = an outage no later AAA notice has closed. A post that changes the rationing plan is reviewed by our water desk before the schedule above changes.
Drought, town by town
The 7 outlined towns are in AAA’s service rotation. Zones 1 and 2 are sector-level within each town — tap a highlighted town to jump to its sector lists.
The 19 dots are AAA’s reservoirs at this morning’s reading — safe, watch, adjustments, control, spilling. Tap a dot for that reservoir’s row on the board below.
Extreme drought (D3): Aguas Buenas, Aibonito, Cabo Rojo, Caguas, Canovanas, Carolina, Catano, Cayey, Ceiba, Coamo, Culebra, Fajardo, Guanica, Guayanilla, Guaynabo, Gurabo, Humacao, Juana Diaz, Juncos, Lajas, Las Piedras, Loiza, Naguabo, Penuelas, Ponce, Rio Grande, Sabana Grande, Salinas, San German, San Juan, San Lorenzo, Santa Isabel, Trujillo Alto, Vieques, Villalba, Yauco
The reservoirs, every morning
Week 7 of the metro rotation, as of Sep 21: 14 of 19 reservoirs sit in seguridad or above, 4 in observación; La Plata is in ajustes.
AAA 5:00 AM reading · September 21. Levels in meters above sea level; change is against the previous morning. The hollow tick on each gauge marks the level about a week back — the gap to NOW is the drift. Each bar reads like a fuel gauge — fuller is better — and the pale zones behind it are AAA’s alert bands, worst at the left. Hover a bar for its exact thresholds.
Behind the rationing
- Carraízo179kServes San Juan, Trujillo Alto, Carolina, Canóvanas, GuraboSeguridadSafe40.79 m −0.02 m−0.05%
History
Date Level Change % Sep 21 40.79 m −0.02 −0.05% Sep 20 40.81 m +0.01 +0.02% Sep 19 40.80 m +0.16 +0.39% Sep 18 40.64 m +0.58 +1.45% Sep 17 40.06 m +0.83 +2.12% Sep 16 39.23 m −0.02 −0.05% Sep 15 39.25 m +0.09 +0.23% Dotted levels were checked against the USGS dam gauge — hover or tap one for its 5:00 AM reading.
23 earlier days
Date Level Change % Sep 14 39.16 m +0.02 +0.05% Sep 13 39.14 m −0.05 −0.13% Sep 12 39.19 m −0.01 −0.03% Sep 11 39.20 m +0.13 +0.33% Sep 10 39.07 m +0.05 +0.13% Sep 9 39.02 m +0.19 +0.49% Sep 8 38.83 m −0.04 −0.10% Sep 7 38.87 m −0.07 −0.18% Sep 6 38.94 m −0.07 −0.18% Sep 5 39.01 m −0.08 −0.20% Sep 4 39.09 m −0.02 −0.05% Sep 3 39.11 m +0.19 +0.49% Sep 2 38.92 m +1.72 +4.62% Sep 1 37.20 m +0.06 +0.16% Aug 31 37.14 m +0.07 +0.19% Aug 30 37.07 m −0.07 −0.19% Aug 29 37.14 m −0.06 −0.16% Aug 28 37.20 m −0.06 −0.16% Aug 27 37.26 m −0.04 −0.11% Aug 26 37.30 m −0.02 −0.05% Aug 25 37.32 m −0.02 −0.05% Aug 24 37.34 m −0.07 −0.19% Aug 23 37.41 m — — - La Plata131kServes Dorado, Guaynabo, Naranjito, Toa Alta, Toa Baja, Vega Alta, Bayamón, Cataño, CorozalAjustesAdjustments44.70 m +0.04 m+0.09%
History
Date Level Change % Sep 21 44.70 m +0.04 +0.09% Sep 20 44.66 m +0.05 +0.11% Sep 19 44.61 m +0.21 +0.47% Sep 18 44.40 m +0.04 +0.09% Sep 17 44.36 m −0.04 −0.09% Sep 16 44.40 m −0.06 −0.13% Sep 15 44.46 m +0.06 +0.14% Dotted levels were checked against the USGS dam gauge — hover or tap one for its 5:00 AM reading.
23 earlier days
Date Level Change % Sep 14 44.40 m +0.14 +0.32% Sep 13 44.26 m +0.01 +0.02% Sep 12 44.25 m +0.11 +0.25% Sep 11 44.14 m −0.10 −0.23% Sep 10 44.24 m −0.08 −0.18% Sep 9 44.32 m −0.08 −0.18% Sep 8 44.40 m −0.06 −0.13% Sep 7 44.46 m −0.06 −0.13% Sep 6 44.52 m −0.02 −0.04% Sep 5 44.54 m −0.03 −0.07% Sep 4 44.57 m −0.02 −0.04% Sep 3 44.59 m ±0.00 ±0.00% Sep 2 44.59 m ±0.00 ±0.00% Sep 1 44.59 m −0.08 −0.18% Aug 31 44.67 m −0.05 −0.11% Aug 30 44.72 m −0.11 −0.25% Aug 29 44.83 m −0.10 −0.22% Aug 28 44.93 m −0.11 −0.24% Aug 27 45.04 m −0.11 −0.24% Aug 26 45.15 m −0.08 −0.18% Aug 25 45.23 m −0.05 −0.11% Aug 24 45.28 m −0.07 −0.15% Aug 23 45.35 m — — - Cidra15kServes Aguas Buenas, Caguas, Cayey, CidraObservaciónWatch400.54 m 0.00 m0.00%
History
Date Level Change % Sep 21 400.54 m ±0.00 ±0.00% Sep 20 400.54 m ±0.00 ±0.00% Sep 19 400.54 m +0.01 +0.00% Sep 18 400.53 m +0.08 +0.02% Sep 17 400.45 m +0.17 +0.04% Sep 16 400.28 m +0.01 +0.00% Sep 15 400.27 m +0.01 +0.00% Dotted levels were checked against the USGS dam gauge — hover or tap one for its 5:00 AM reading.
23 earlier days
Date Level Change % Sep 14 400.26 m ±0.00 ±0.00% Sep 13 400.26 m −0.01 −0.00% Sep 12 400.27 m ±0.00 ±0.00% Sep 11 400.27 m +0.05 +0.01% Sep 10 400.22 m +0.04 +0.01% Sep 9 400.18 m +0.02 +0.00% Sep 8 400.16 m ±0.00 ±0.00% Sep 7 400.16 m ±0.00 ±0.00% Sep 6 400.16 m −0.01 −0.00% Sep 5 400.17 m ±0.00 ±0.00% Sep 4 400.17 m ±0.00 ±0.00% Sep 3 400.17 m ±0.00 ±0.00% Sep 2 400.17 m +0.04 +0.01% Sep 1 400.13 m +0.07 +0.02% Aug 31 400.06 m +0.04 +0.01% Aug 30 400.02 m −0.02 −0.00% Aug 29 400.04 m −0.02 −0.00% Aug 28 400.06 m −0.01 −0.00% Aug 27 400.07 m −0.01 −0.00% Aug 26 400.08 m −0.02 −0.00% Aug 25 400.10 m ±0.00 ±0.00% Aug 24 400.10 m −0.01 −0.00% Aug 23 400.11 m — —
Across the island — 16 more reservoirs1 Desborde · 12 Seguridad · 3 Observación
- Fajardo32kServes Ceiba, Fajardo, Luquillo, Río GrandeObservaciónWatch47.44 m 0.00 m0.00%
History
Date Level Change % Sep 21 47.44 m ±0.00 ±0.00% Sep 20 47.44 m ±0.00 ±0.00% Sep 19 47.44 m +0.10 +0.21% Sep 18 47.34 m +0.25 +0.53% Sep 17 47.09 m +0.09 +0.19% Sep 16 47.00 m −0.02 −0.04% Sep 15 47.02 m −0.03 −0.06% 23 earlier days
Date Level Change % Sep 14 47.05 m −0.02 −0.04% Sep 13 47.07 m −0.05 −0.11% Sep 12 47.12 m −0.01 −0.02% Sep 11 47.13 m +0.10 +0.21% Sep 10 47.03 m −0.02 −0.04% Sep 9 47.05 m +0.10 +0.21% Sep 8 46.95 m +0.18 +0.38% Sep 7 46.77 m +0.10 +0.21% Sep 6 46.67 m −0.02 −0.04% Sep 5 46.69 m −0.05 −0.11% Sep 4 46.74 m −0.03 −0.06% Sep 3 46.77 m +0.08 +0.17% Sep 2 46.69 m +0.16 +0.34% Sep 1 46.53 m +0.14 +0.30% Aug 31 46.39 m +0.06 +0.13% Aug 30 46.33 m ±0.00 ±0.00% Aug 29 46.33 m −0.07 −0.15% Aug 28 46.40 m −0.09 −0.19% Aug 27 46.49 m −0.11 −0.24% Aug 26 46.60 m −0.06 −0.13% Aug 25 46.66 m −0.01 −0.02% Aug 24 46.67 m −0.07 −0.15% Aug 23 46.74 m — — - GuayabalJuana Díaz · PREPAObservaciónWatch102.64 m −0.03 m−0.03%
History
Date Level Change % Sep 21 102.64 m −0.03 −0.03% Sep 20 102.67 m +0.01 +0.01% Sep 19 102.66 m +0.01 +0.01% Sep 18 102.65 m +0.04 +0.04% Sep 17 102.61 m −0.04 −0.04% Sep 16 102.65 m −0.03 −0.03% Sep 15 102.68 m −0.02 −0.02% 23 earlier days
Date Level Change % Sep 14 102.70 m −0.04 −0.04% Sep 13 102.74 m −0.04 −0.04% Sep 12 102.78 m −0.03 −0.03% Sep 11 102.81 m +0.02 +0.02% Sep 10 102.79 m −0.02 −0.02% Sep 9 102.81 m +0.04 +0.04% Sep 8 102.77 m −0.05 −0.05% Sep 7 102.82 m −0.05 −0.05% Sep 6 102.87 m −0.05 −0.05% Sep 5 102.92 m −0.06 −0.06% Sep 4 102.98 m −0.02 −0.02% Sep 3 103.00 m +0.20 +0.19% Sep 2 102.80 m +0.25 +0.24% Sep 1 102.55 m +0.05 +0.05% Aug 31 102.50 m +0.11 +0.11% Aug 30 102.39 m −0.02 −0.02% Aug 29 102.41 m −0.02 −0.02% Aug 28 102.43 m −0.01 −0.01% Aug 27 102.44 m −0.02 −0.02% Aug 26 102.46 m −0.02 −0.02% Aug 25 102.48 m −0.02 −0.02% Aug 24 102.50 m −0.02 −0.02% Aug 23 102.52 m — — - Río Blanco29kServes Humacao, Yabucoa, Naguabo, Vieques, CulebraObservaciónWatch25.61 m −0.01 m−0.04%
History
Date Level Change % Sep 21 25.61 m −0.01 −0.04% Sep 20 25.62 m +0.02 +0.08% Sep 19 25.60 m +0.06 +0.23% Sep 18 25.54 m +0.21 +0.83% Sep 17 25.33 m +0.08 +0.32% Sep 16 25.25 m −0.02 −0.08% Sep 15 25.27 m −0.02 −0.08% 23 earlier days
Date Level Change % Sep 14 25.29 m −0.03 −0.12% Sep 13 25.32 m −0.02 −0.08% Sep 12 25.34 m ±0.00 ±0.00% Sep 11 25.34 m +0.11 +0.44% Sep 10 25.23 m +0.02 +0.08% Sep 9 25.21 m +0.09 +0.36% Sep 8 25.12 m +0.09 +0.36% Sep 7 25.03 m +0.13 +0.52% Sep 6 24.90 m +0.05 +0.20% Sep 5 24.85 m −0.04 −0.16% Sep 4 24.89 m −0.02 −0.08% Sep 3 24.91 m ±0.00 ±0.00% Sep 2 24.91 m +0.15 +0.61% Sep 1 24.76 m +0.27 +1.10% Aug 31 24.49 m +0.19 +0.78% Aug 30 24.30 m −0.06 −0.25% Aug 29 24.36 m −0.06 −0.25% Aug 28 24.42 m −0.07 −0.29% Aug 27 24.49 m −0.07 −0.29% Aug 26 24.56 m −0.06 −0.24% Aug 25 24.62 m −0.01 −0.04% Aug 24 24.63 m −0.05 −0.20% Aug 23 24.68 m — — - CaonillasUtuado · PREPASeguridadSafe251.80 m −0.02 m−0.01%
History
Date Level Change % Sep 21 251.80 m −0.02 −0.01% Sep 20 251.82 m ±0.00 ±0.00% Sep 19 251.82 m ±0.00 ±0.00% Sep 18 251.82 m +0.02 +0.01% Sep 17 251.80 m +0.01 +0.00% Sep 16 251.79 m +0.04 +0.02% Sep 15 251.75 m +0.05 +0.02% 23 earlier days
Date Level Change % Sep 14 251.70 m +0.04 +0.02% Sep 13 251.66 m +0.03 +0.01% Sep 12 251.63 m +0.04 +0.02% Sep 11 251.59 m +0.07 +0.03% Sep 10 251.52 m +0.05 +0.02% Sep 9 251.47 m +0.06 +0.02% Sep 8 251.41 m +0.04 +0.02% Sep 7 251.37 m +0.04 +0.02% Sep 6 251.33 m +0.05 +0.02% Sep 5 251.28 m +0.06 +0.02% Sep 4 251.22 m +0.14 +0.06% Sep 3 251.08 m +0.47 +0.19% Sep 2 250.61 m +0.05 +0.02% Sep 1 250.56 m +0.03 +0.01% Aug 31 250.53 m +0.05 +0.02% Aug 30 250.48 m +0.02 +0.01% Aug 29 250.46 m −0.29 −0.12% Aug 28 250.75 m −0.52 −0.21% Aug 27 251.27 m +0.02 +0.01% Aug 26 251.25 m +0.03 +0.01% Aug 25 251.22 m +0.07 +0.03% Aug 24 251.15 m +0.03 +0.01% Aug 23 251.12 m — — - Carite15kServes Caguas, Cayey, Cidra, Guayama, Patillas, San LorenzoSeguridadSafe542.37 m −0.01 m−0.00%
History
Date Level Change % Sep 21 542.37 m −0.01 −0.00% Sep 20 542.38 m −0.01 −0.00% Sep 19 542.39 m +0.01 +0.00% Sep 18 542.38 m +0.10 +0.02% Sep 17 542.28 m +0.06 +0.01% Sep 16 542.22 m −0.02 −0.00% Sep 15 542.24 m ±0.00 ±0.00% 23 earlier days
Date Level Change % Sep 14 542.24 m ±0.00 ±0.00% Sep 13 542.24 m −0.01 −0.00% Sep 12 542.25 m ±0.00 ±0.00% Sep 11 542.25 m +0.16 +0.03% Sep 10 542.09 m +0.08 +0.01% Sep 9 542.01 m ±0.00 ±0.00% Sep 8 542.01 m +0.04 +0.01% Sep 7 541.97 m −0.02 −0.00% Sep 6 541.99 m −0.01 −0.00% Sep 5 542.00 m −0.01 −0.00% Sep 4 542.01 m −0.01 −0.00% Sep 3 542.02 m −0.01 −0.00% Sep 2 542.03 m +0.11 +0.02% Sep 1 541.92 m +0.22 +0.04% Aug 31 541.70 m +0.02 +0.00% Aug 30 541.68 m −0.02 −0.00% Aug 29 541.70 m −0.02 −0.00% Aug 28 541.72 m −0.01 −0.00% Aug 27 541.73 m −0.02 −0.00% Aug 26 541.75 m −0.01 −0.00% Aug 25 541.76 m −0.02 −0.00% Aug 24 541.78 m −0.01 −0.00% Aug 23 541.79 m — — - Cerrillos51kServes Ponce, PeñuelasSeguridadSafe167.04 m −0.05 m−0.03%
History
Date Level Change % Sep 21 167.04 m −0.05 −0.03% Sep 20 167.09 m −0.02 −0.01% Sep 19 167.11 m −0.03 −0.02% Sep 18 167.14 m ±0.00 ±0.00% Sep 17 167.14 m −0.04 −0.02% Sep 16 167.18 m −0.03 −0.02% Sep 15 167.21 m −0.02 −0.01% 23 earlier days
Date Level Change % Sep 14 167.23 m −0.04 −0.02% Sep 13 167.27 m −0.05 −0.03% Sep 12 167.32 m −0.04 −0.02% Sep 11 167.36 m −0.03 −0.02% Sep 10 167.39 m −0.03 −0.02% Sep 9 167.42 m −0.01 −0.01% Sep 8 167.43 m −0.03 −0.02% Sep 7 167.46 m −0.04 −0.02% Sep 6 167.50 m −0.03 −0.02% Sep 5 167.53 m −0.02 −0.01% Sep 4 167.55 m +0.03 +0.02% Sep 3 167.52 m +0.28 +0.17% Sep 2 167.24 m −0.05 −0.03% Sep 1 167.29 m +0.03 +0.02% Aug 31 167.26 m −0.01 −0.01% Aug 30 167.27 m −0.04 −0.02% Aug 29 167.31 m −0.06 −0.04% Aug 28 167.37 m −0.04 −0.02% Aug 27 167.41 m −0.04 −0.02% Aug 26 167.45 m −0.04 −0.02% Aug 25 167.49 m −0.01 −0.01% Aug 24 167.50 m −0.05 −0.03% Aug 23 167.55 m — — - Dos BocasArecibo · PREPASeguridadSafe89.67 m +0.21 m+0.23%
History
Date Level Change % Sep 21 89.67 m +0.21 +0.23% Sep 20 89.46 m +0.30 +0.34% Sep 19 89.16 m +0.13 +0.15% Sep 18 89.03 m +0.06 +0.07% Sep 17 88.97 m +0.11 +0.12% Sep 16 88.86 m +0.03 +0.03% Sep 15 88.83 m −0.12 −0.13% 23 earlier days
Date Level Change % Sep 14 88.95 m −0.21 −0.24% Sep 13 89.16 m −0.45 −0.50% Sep 12 89.61 m −0.19 −0.21% Sep 11 89.80 m −0.02 −0.02% Sep 10 89.82 m ±0.00 ±0.00% Sep 9 89.82 m −0.02 −0.02% Sep 8 89.84 m −0.11 −0.12% Sep 7 89.95 m +0.11 +0.12% Sep 6 89.84 m +0.14 +0.16% Sep 5 89.70 m −0.26 −0.29% Sep 4 89.96 m −0.08 −0.09% Sep 3 90.04 m +0.40 +0.45% Sep 2 89.64 m −0.08 −0.09% Sep 1 89.72 m +0.05 +0.06% Aug 31 89.67 m +0.01 +0.01% Aug 30 89.66 m −0.12 −0.13% Aug 29 89.78 m +0.44 +0.49% Aug 28 89.34 m +0.71 +0.80% Aug 27 88.63 m −0.10 −0.11% Aug 26 88.73 m +0.08 +0.09% Aug 25 88.65 m +0.09 +0.10% Aug 24 88.56 m +0.13 +0.15% Aug 23 88.43 m — — - GarzasAdjuntas · PREPASeguridadSafe736.07 m 0.00 m0.00%
History
Date Level Change % Sep 21 736.07 m ±0.00 ±0.00% Sep 20 736.07 m ±0.00 ±0.00% Sep 19 736.07 m −0.03 −0.00% Sep 18 736.10 m +0.05 +0.01% Sep 17 736.05 m −0.02 −0.00% Sep 16 736.07 m +0.01 +0.00% Sep 15 736.06 m +0.02 +0.00% 23 earlier days
Date Level Change % Sep 14 736.04 m +0.05 +0.01% Sep 13 735.99 m −0.03 −0.00% Sep 12 736.02 m −0.04 −0.01% Sep 11 736.06 m +0.03 +0.00% Sep 10 736.03 m −0.04 −0.01% Sep 9 736.07 m +0.01 +0.00% Sep 8 736.06 m ±0.00 ±0.00% Sep 7 736.06 m ±0.00 ±0.00% Sep 6 736.06 m +0.01 +0.00% Sep 5 736.05 m −0.05 −0.01% Sep 4 736.10 m +0.02 +0.00% Sep 3 736.08 m +0.02 +0.00% Sep 2 736.06 m +0.03 +0.00% Sep 1 736.03 m −0.04 −0.01% Aug 31 736.07 m +0.02 +0.00% Aug 30 736.05 m +0.02 +0.00% Aug 29 736.03 m −0.04 −0.01% Aug 28 736.07 m ±0.00 ±0.00% Aug 27 736.07 m +0.01 +0.00% Aug 26 736.06 m −0.01 −0.00% Aug 25 736.07 m +0.07 +0.01% Aug 24 736.00 m +0.02 +0.00% Aug 23 735.98 m — — - Guajataca63kServes Moca, Aguadilla, Aguada, Isabela, San Sebastián, Quebradillas, Bo. Puntas de RincónSeguridadSafe196.26 m +0.17 m+0.09%
History
Date Level Change % Sep 21 196.26 m +0.17 +0.09% Sep 20 196.09 m +0.01 +0.01% Sep 19 196.08 m −0.02 −0.01% Sep 18 196.10 m −0.01 −0.01% Sep 17 196.11 m −0.03 −0.02% Sep 16 196.14 m −0.02 −0.01% Sep 15 196.16 m −0.02 −0.01% 23 earlier days
Date Level Change % Sep 14 196.18 m −0.02 −0.01% Sep 13 196.20 m −0.02 −0.01% Sep 12 196.22 m −0.03 −0.02% Sep 11 196.25 m −0.01 −0.01% Sep 10 196.26 m ±0.00 ±0.00% Sep 9 196.26 m +0.35 +0.18% Sep 8 195.91 m ±0.00 ±0.00% Sep 7 195.91 m ±0.00 ±0.00% Sep 6 195.91 m ±0.00 ±0.00% Sep 5 195.91 m −0.02 −0.01% Sep 4 195.93 m ±0.00 ±0.00% Sep 3 195.93 m +0.03 +0.02% Sep 2 195.90 m ±0.00 ±0.00% Sep 1 195.90 m +0.01 +0.01% Aug 31 195.89 m +0.02 +0.01% Aug 30 195.87 m −0.03 −0.02% Aug 29 195.90 m −0.01 −0.01% Aug 28 195.91 m −0.02 −0.01% Aug 27 195.93 m −0.02 −0.01% Aug 26 195.95 m ±0.00 ±0.00% Aug 25 195.95 m +0.02 +0.01% Aug 24 195.93 m ±0.00 ±0.00% Aug 23 195.93 m — — - GuayoLares · PREPASeguridadSafe442.78 m −0.09 m−0.02%
History
Date Level Change % Sep 21 442.78 m −0.09 −0.02% Sep 20 442.87 m −0.06 −0.01% Sep 19 442.93 m −0.03 −0.01% Sep 18 442.96 m ±0.00 ±0.00% Sep 17 442.96 m −0.02 −0.00% Sep 16 442.98 m +0.06 +0.01% Sep 15 442.92 m +0.12 +0.03% 23 earlier days
Date Level Change % Sep 14 442.80 m +0.07 +0.02% Sep 13 442.73 m +0.04 +0.01% Sep 12 442.69 m +0.05 +0.01% Sep 11 442.64 m +0.04 +0.01% Sep 10 442.60 m +0.05 +0.01% Sep 9 442.55 m +0.05 +0.01% Sep 8 442.50 m −2.51 −0.56% Sep 7 445.01 m +2.60 +0.59% Sep 6 442.41 m +0.06 +0.01% Sep 5 442.35 m +0.08 +0.02% Sep 4 442.27 m +0.14 +0.03% Sep 3 442.13 m −0.02 −0.00% Sep 2 442.15 m −0.39 −0.09% Sep 1 442.54 m −0.18 −0.04% Aug 31 442.72 m +0.06 +0.01% Aug 30 442.66 m +0.06 +0.01% Aug 29 442.60 m +0.08 +0.02% Aug 28 442.52 m +0.07 +0.02% Aug 27 442.45 m +0.04 +0.01% Aug 26 442.41 m +0.06 +0.01% Aug 25 442.35 m +0.06 +0.01% Aug 24 442.29 m +0.06 +0.01% Aug 23 442.23 m — — - LocoYauco · PREPASeguridadSafe69.64 m +0.16 m+0.23%
History
Date Level Change % Sep 21 69.64 m +0.15 +0.22% Sep 20 69.49 m +0.26 +0.38% Sep 19 69.23 m +0.02 +0.03% Sep 18 69.21 m −0.07 −0.10% Sep 17 69.28 m −0.17 −0.24% Sep 16 69.45 m −0.10 −0.14% Sep 15 69.55 m +0.04 +0.06% 23 earlier days
Date Level Change % Sep 14 69.51 m −0.39 −0.56% Sep 13 69.90 m +0.41 +0.59% Sep 12 69.49 m −0.02 −0.03% Sep 11 69.51 m ±0.00 ±0.00% Sep 10 69.51 m −0.14 −0.20% Sep 9 69.65 m −0.01 −0.01% Sep 8 69.66 m +0.09 +0.13% Sep 7 69.57 m +0.01 +0.01% Sep 6 69.56 m ±0.00 ±0.00% Sep 5 69.56 m +0.10 +0.14% Sep 4 69.46 m +0.01 +0.01% Sep 3 69.45 m −0.04 −0.06% Sep 2 69.49 m +0.06 +0.09% Sep 1 69.43 m +0.07 +0.10% Aug 31 69.36 m −0.06 −0.09% Aug 30 69.42 m −0.29 −0.42% Aug 29 69.71 m −0.40 −0.57% Aug 28 70.11 m −0.02 −0.03% Aug 27 70.13 m −0.02 −0.03% Aug 26 70.15 m +0.17 +0.24% Aug 25 69.98 m +0.06 +0.09% Aug 24 69.92 m +0.02 +0.03% Aug 23 69.90 m — — - LucchettiYauco · PREPASeguridadSafe171.48 m +0.09 m+0.05%
History
Date Level Change % Sep 21 171.48 m +0.09 +0.05% Sep 20 171.39 m +0.10 +0.06% Sep 19 171.29 m +0.12 +0.07% Sep 18 171.17 m +0.15 +0.09% Sep 17 171.02 m +0.12 +0.07% Sep 16 170.90 m +0.06 +0.04% Sep 15 170.84 m −0.08 −0.05% 23 earlier days
Date Level Change % Sep 14 170.92 m +0.04 +0.02% Sep 13 170.88 m −0.13 −0.08% Sep 12 171.01 m −0.09 −0.05% Sep 11 171.10 m −0.09 −0.05% Sep 10 171.19 m −0.07 −0.04% Sep 9 171.26 m −0.07 −0.04% Sep 8 171.33 m −0.10 −0.06% Sep 7 171.43 m −0.07 −0.04% Sep 6 171.50 m −0.07 −0.04% Sep 5 171.57 m −0.07 −0.04% Sep 4 171.64 m −0.01 −0.01% Sep 3 171.65 m +0.14 +0.08% Sep 2 171.51 m +0.36 +0.21% Sep 1 171.15 m +0.16 +0.09% Aug 31 170.99 m −0.01 −0.01% Aug 30 171.00 m −0.04 −0.02% Aug 29 171.04 m −0.03 −0.02% Aug 28 171.07 m −0.10 −0.06% Aug 27 171.17 m −0.10 −0.06% Aug 26 171.27 m −0.11 −0.06% Aug 25 171.38 m −0.08 −0.05% Aug 24 171.46 m −0.08 −0.05% Aug 23 171.54 m — — - MatrullasOrocovis · PREPASeguridadSafe734.93 m +0.02 m+0.00%
History
Date Level Change % Sep 21 734.93 m +0.02 +0.00% Sep 20 734.91 m +0.02 +0.00% Sep 19 734.89 m +0.03 +0.00% Sep 18 734.86 m +0.12 +0.02% Sep 17 734.74 m +0.01 +0.00% Sep 16 734.73 m +0.02 +0.00% Sep 15 734.71 m +0.02 +0.00% 23 earlier days
Date Level Change % Sep 14 734.69 m +0.01 +0.00% Sep 13 734.68 m +0.02 +0.00% Sep 12 734.66 m +0.02 +0.00% Sep 11 734.64 m +0.16 +0.02% Sep 10 734.48 m +0.08 +0.01% Sep 9 734.40 m +0.02 +0.00% Sep 8 734.38 m +0.03 +0.00% Sep 7 734.35 m +0.04 +0.01% Sep 6 734.31 m +0.01 +0.00% Sep 5 734.30 m +0.02 +0.00% Sep 4 734.28 m +0.07 +0.01% Sep 3 734.21 m +0.78 +0.11% Sep 2 733.43 m +0.22 +0.03% Sep 1 733.21 m +0.05 +0.01% Aug 31 733.16 m +0.04 +0.01% Aug 30 733.12 m ±0.00 ±0.00% Aug 29 733.12 m −0.01 −0.00% Aug 28 733.13 m ±0.00 ±0.00% Aug 27 733.13 m ±0.00 ±0.00% Aug 26 733.13 m +0.01 +0.00% Aug 25 733.12 m +0.03 +0.00% Aug 24 733.09 m −0.02 −0.00% Aug 23 733.11 m — — - Patillas14kServes Arroyo, Guayama, Maunabo, PatillasSeguridadSafe65.61 m −0.02 m−0.03%
History
Date Level Change % Sep 21 65.61 m −0.02 −0.03% Sep 20 65.63 m −0.02 −0.03% Sep 19 65.65 m −0.04 −0.06% Sep 18 65.69 m +0.03 +0.05% Sep 17 65.66 m +0.09 +0.14% Sep 16 65.57 m −0.04 −0.06% Sep 15 65.61 m −0.04 −0.06% 23 earlier days
Date Level Change % Sep 14 65.65 m −0.04 −0.06% Sep 13 65.69 m −0.10 −0.15% Sep 12 65.79 m −0.22 −0.33% Sep 11 66.01 m +0.13 +0.20% Sep 10 65.88 m −0.06 −0.09% Sep 9 65.94 m +0.01 +0.02% Sep 8 65.93 m +0.12 +0.18% Sep 7 65.81 m −0.03 −0.05% Sep 6 65.84 m −0.02 −0.03% Sep 5 65.86 m −0.01 −0.02% Sep 4 65.87 m ±0.00 ±0.00% Sep 3 65.87 m +0.02 +0.03% Sep 2 65.85 m +0.64 +0.98% Sep 1 65.21 m +1.84 +2.90% Aug 31 63.37 m +0.05 +0.08% Aug 30 63.32 m −0.02 −0.03% Aug 29 63.34 m −0.02 −0.03% Aug 28 63.36 m −0.03 −0.05% Aug 27 63.39 m −0.02 −0.03% Aug 26 63.41 m −0.03 −0.05% Aug 25 63.44 m −0.01 −0.02% Aug 24 63.45 m −0.02 −0.03% Aug 23 63.47 m — — - Toa Vaca19kServes Ponce, Juana Díaz, Coamo, VillalbaSeguridadSafe147.17 m −0.01 m−0.01%
History
Date Level Change % Sep 21 147.17 m −0.01 −0.01% Sep 20 147.18 m +0.03 +0.02% Sep 19 147.15 m ±0.00 ±0.00% Sep 18 147.15 m +0.01 +0.01% Sep 17 147.14 m −0.01 −0.01% Sep 16 147.15 m −0.02 −0.01% Sep 15 147.17 m ±0.00 ±0.00% 23 earlier days
Date Level Change % Sep 14 147.17 m −0.02 −0.01% Sep 13 147.19 m −0.01 −0.01% Sep 12 147.20 m −0.01 −0.01% Sep 11 147.21 m +0.03 +0.02% Sep 10 147.18 m −0.01 −0.01% Sep 9 147.19 m +0.02 +0.01% Sep 8 147.17 m −0.01 −0.01% Sep 7 147.18 m −0.02 −0.01% Sep 6 147.20 m −0.01 −0.01% Sep 5 147.21 m −0.01 −0.01% Sep 4 147.22 m ±0.00 ±0.00% Sep 3 147.22 m +0.07 +0.05% Sep 2 147.15 m +0.04 +0.03% Sep 1 147.11 m −0.01 −0.01% Aug 31 147.12 m ±0.00 ±0.00% Aug 30 147.12 m −0.02 −0.01% Aug 29 147.14 m −0.02 −0.01% Aug 28 147.16 m −0.02 −0.01% Aug 27 147.18 m −0.02 −0.01% Aug 26 147.20 m −0.02 −0.01% Aug 25 147.22 m −0.02 −0.01% Aug 24 147.24 m −0.02 −0.01% Aug 23 147.26 m — — - GuineoOrocovis · PREPADesbordeSpilling902.42 m −0.01 m−0.00%
History
Date Level Change % Sep 21 902.42 m −0.01 −0.00% Sep 20 902.43 m ±0.00 ±0.00% Sep 19 902.43 m −0.02 −0.00% Sep 18 902.45 m +0.03 +0.00% Sep 17 902.42 m ±0.00 ±0.00% Sep 16 902.42 m −0.01 −0.00% Sep 15 902.43 m +0.01 +0.00% 23 earlier days
Date Level Change % Sep 14 902.42 m +0.21 +0.02% Sep 13 902.21 m −0.21 −0.02% Sep 12 902.42 m −0.01 −0.00% Sep 11 902.43 m +0.22 +0.02% Sep 10 902.21 m ±0.00 ±0.00% Sep 9 902.21 m ±0.00 ±0.00% Sep 8 902.21 m −0.09 −0.01% Sep 7 902.30 m +0.01 +0.00% Sep 6 902.29 m +0.02 +0.00% Sep 5 902.27 m +0.02 +0.00% Sep 4 902.25 m +0.04 +0.00% Sep 3 902.21 m +0.39 +0.04% Sep 2 901.82 m +0.09 +0.01% Sep 1 901.73 m +0.21 +0.02% Aug 31 901.52 m +0.03 +0.00% Aug 30 901.49 m ±0.00 ±0.00% Aug 29 901.49 m +0.01 +0.00% Aug 28 901.48 m +0.04 +0.00% Aug 27 901.44 m ±0.00 ±0.00% Aug 26 901.44 m +0.01 +0.00% Aug 25 901.43 m +0.01 +0.00% Aug 24 901.42 m +0.02 +0.00% Aug 23 901.40 m — —
AAA’s alert bands, fullest to emptiest:
- Desborde — at the spillway, releasing excess
- Seguridad — normal supply
- Observación — below normal; conservation urged
- Ajustes — operational adjustments, like pressure cuts
- Control — drought controls; rationing-level measures
- Fuera de servicio — too low to draw from
The solid bar is today’s level; the pale zones behind it are the bands it moves through. The red line is labeled with the band the reservoir falls into below that level, and the green number is the full line.
Source: Autoridad de Acueductos y Alcantarillados, daily reservoir monitoring.
Open data: these readings are yours to reuse — current state (JSON) · full history (CSV) · history (JSON) · MCP tools for AI assistants. CC BY 4.0: credit 787daily.com and AAA.
Rain over the watershedsUSGS gauges · updated 12:45 PM AST
- CarraízoToday0.00 inLast 24 h0.00 in
- La PlataToday0.01 inLast 24 h0.01 inOver 24 h: Rio De La Plata below Represa Comerio · 6 km away · wettest of 3
- CidraToday0.04 inLast 24 h0.04 inOver 24 h: Bo. Rabanal raingage At Cidra · 4 km away · wettest of 11
- IslandwideToday11 wetLast 24 h14 wetof 54 reporting · max 2.77 in · Bo Guajataca raingage above Lago Guajataca At Pr 455
fell today (since midnight AST) earlier in the trailing 24 h
Each tube is a rain gauge marked every quarter inch and brim-full at 1.00 in — the same scale on every watershed, so the columns are comparable. The islandwide tube is the share of gauges reporting rain.
Every reporting gauge (54)
- Bo Guajataca raingage above Lago Guajataca At Pr 455 → Guajataca0.012.77
- Lago Regulador De Isabela nr Hwy 112 Isabela0.002.19
- Rio Tanama nr Utuado0.001.25
- Lago Patillas At Damsite Near Patillas → Patillas0.350.35
- Rio Guajataca At Lares → Guajataca0.010.26
- Lago Melania Near Guayama → Carite0.020.14
- Jua 5 Well, Guayama0.010.11
- Bo. Rabanal raingage At Cidra → Cidra0.040.04
- Rio Cerrillos above Lago Cerrillos nr Ponce → Cerrillos0.040.04
- Rio Portugues At Parque Ceremonial Tibes nr Ponce → Cerrillos0.000.04
- Stormwater Station Fuel Dispensing,Salinas0.010.01
- Lago Carite At Spillway → Carite0.010.01
- Rio De La Plata below Represa Comerio → La Plata0.010.01
- Pueblito Del Rio raingage, Las Piedras → Río Blanco0.010.01
40 more gauges reported 0.00 in over the last 24 h.
Source: USGS National Water Information System, 15-minute precipitation. Today is midnight AST to now; last 24 h is the trailing 24 hours, so it can include yesterday evening's rain that today's column has already left behind. Watershed rows show the highest reading among the gauges within 12 km of the reservoir — a proximity read, not a basin boundary. Each window is measured on its own, so the wettest gauge since midnight is not always the one leading the 24-hour total; the named gauge is the 24-hour leader.
Tomorrow's water picture, in your inbox
The morning brief carries the reservoir levels, the rationing status and any AAA change overnight — plus the day's news, weather and surf. Free, daily, unsubscribe anytime.
Check your inbox
We sent a confirmation link. Tap it and tomorrow's brief will be waiting for you in the morning. (Nothing arrives until you confirm — that's on purpose.)