LUMA Energy told the Puerto Rico Energy Bureau that its October 2026 reconciliation shows a $45,148,207.09 shortfall in the fuel adjustment clause (FCA) and a $2,242,635.83 credit to customers in the purchased power adjustment clause (PPCA), according to an informational motion filed on November 17. Combining September and October, the two-month period shows a total FCA shortfall of $99,522,168.30 and PPCA credits of $8,596,039.12, for a net amount of $90,926,129.18 that would have to be recovered from customers.
LUMA anticipates the amounts will be addressed through the applicable quarterly adjustment process, subject to review and approval by the Energy Bureau. The filing was made in the case on the permanent rate of the Puerto Rico Electric Power Authority (PREPA; AEE in Spanish). LUMA attributed the variations in fuel costs to higher diesel consumption, increased consumption due to above-normal temperatures, natural gas supply problems that forced prolonged diesel use at the San Juan combined-cycle units, and unexpected problems in the generation fleet, including the forced outage of large units.
The company states that it neither owns nor operates generation facilities, does not buy fuel for generation, and does not determine the impact of those costs on rates.