Infrastructure

Puerto Rico Energy Bureau Demands More Data from LUMA, Genera on Proposed Power Bill Hike

Published Sep 25, 2026, 4:25 PM ASTvia Metro PR

At a glance

  • The Puerto Rico Energy Bureau has requested additional information from LUMA Energy, Genera PR, and PREPA on fuel cost calculations.
  • LUMA had requested a rate increase that could result in a $48 hike in residential bills and a $70 increase in commercial bills.
  • The entities must respond by September 29 and report any changes in gas supply or projections without further order.

Why this matters: For Puerto Rico households and businesses, the proposed rate hike could mean higher electricity bills, affecting their cost of living and economic stability.

Our coverage

Power live: 1,411 customers out island-wide at 11:37 PM

The Puerto Rico Energy Bureau (NEPR) ordered LUMA Energy, Genera PR and the Puerto Rico Electric Power Authority (PREPA) to answer a fourth information request about their fuel cost calculations, days before a scheduled conference on a proposed six-cent-per-kilowatt-hour increase to electricity bills. The Resolution and Order, issued September 25, requires the entities to explain differences between two fuel cost projections, how gas quantities (available, consumed, billed and credited) were calculated, and details on the natural gas supply interruption at San Juan delivery points since September 16, plus the operation of diesel units.

The Bureau questioned whether billed-but-unconsumed gas costs were included in the fuel adjustment reconciliation, given that gas wasn’t available at San Juan delivery points when the projection assumed several units would run mainly on natural gas. A virtual technical conference is set for Monday, September 28 at 10:00 AM, following LUMA’s request last week for an increase that could reach $48 on residential bills and $70 on commercial bills.

Full responses are due by Tuesday, September 29, with any incomplete answers requiring identification of who holds the missing data and when it will be delivered. The entities must also report, without further order, any changes in gas supply, fuel projections, or vessel arrivals/departures related to the San Juan terminal.

In context (787daily, from public data)

SourceMetro PR

Follow this story

Our coverage

Power live: 1,411 customers out island-wide at 11:37 PM

  1. · La Perla del SurNEPR Orders LUMA and Genera to Explain Requested Increase

More in Infrastructure