Infrastructure

EcoEléctrica Aims to Extend Its Stay in Puerto Rico Beyond 2045

Published Oct 15, 2026, 5:45 AM ASTvia NotiCel

At a glance

  • EcoEléctrica has begun studying its assets for a potential contract extension with PREPA beyond 2032, as stated by Carlos Reyes Berríos
  • The company expects conversations about the contract extension to begin as early as 2027, according to Reyes Berríos
  • EcoEléctrica’s maintenance costs are covered by the company’s budget, but $16 to $17 million is assumed in the customer’s bill each month for fuel payments, as noted by Jorge Cotto

Why this matters: For Puerto Rico’s households and businesses, the potential extension of EcoEléctrica’s contract could impact the island’s energy landscape and costs beyond 2032, affecting the overall economy and cost of living.

Our coverage

Power live: 1,878 customers out island-wide at 11:32 PM

In Puerto Rico, EcoEléctrica, a private power generator, has begun studying the current conditions and remaining useful life of its critical assets, with the goal of potentially extending its contract with the Puerto Rico Electric Power Authority (PREPA; AEE in Spanish) beyond 2032. The company’s president, Carlos Reyes Berríos, stated that the term of a new contract will depend on the capacity of the electrical system with new generation resources.

EcoEléctrica currently provides 561 megawatts of contracted capacity to the electrical system. Reyes Berríos expects conversations about the contract extension to begin as early as 2027. The company has presented a timeline with the planned sequence of work, including major interventions between 2030 and 2032.

The Puerto Rico House of Representatives’ Government Committee held a public hearing on the matter, where Reyes Berríos clarified that the company’s maintenance costs, between $20 and $30 million annually, are covered by the company’s budget and not passed on to customers. However, the PREPA’s Operations Administrator, Jorge Cotto, noted that $16 to $17 million is assumed in the customer’s bill each month for the payment of two ships that supply fuel to EcoEléctrica and the Costa Sur Power Plant.

In context (787daily, from public data)

  • LUMA's portal showed 0.2% of customers out at 6:06 AM AST on Oct 18, 2026. Across the 42 days 787daily has tracked it, the daily average is 0.3% and the worst was 1.8% on Sep 30, 2026.

    LUMA Energy outage portal · Oct 18, 6:06 AM AST
  • Customers averaged 28.4 hours without power in the fiscal year that ended in June 2026, the worst of the five full years LUMA has run the grid and up from 26.3 hours the year before.

    LUMA operates the transmission and distribution system.

    PR Energy Bureau, as filed by LUMA · fiscal year ending June 2026
SourceNotiCel

Our coverage

Power live: 1,878 customers out island-wide at 11:32 PM