Oversight Board Tells Federal Court Power Expectations Request to Block PREPA Deal Violates PROMESA

Published Nov 23, 2026, 7:41 AM ASTvia NotiUno

At a glance

  • The Oversight Board told a federal court that Power Expectations LLC’s request to bar PREPA from negotiating another 400-megawatt temporary generation deal at Aguirre violates section 305 of PROMESA, approved in June 2016.
  • The board’s lawyers said the remedy would stop PREPA from contracting any other provider with temporary generation capacity at Aguirre, favoring a party whose contract the board canceled.
  • The canceled contract was valued at $5.9 billion and had gone to a consortium of Power Expectations LLC, Enchanted Rock and Reyes Contractor Group; eRock accused Power Expectations of threats, extortion and unauthorized use of signatures.

Why this matters: The fight centers on 400 megawatts of temporary generation at Aguirre, capacity that feeds PREPA’s grid while the island’s permanent plants and the pending privatization of generation remain unresolved.

Our coverage

Power live: 4,457 customers out island-wide at 4:53 AM

Puerto Rico’s Financial Oversight Board told the federal court that the remedy sought by Power Expectations LLC would violate the Puerto Rico Oversight, Management, and Economic Stability Act (PROMESA). The company wants PREPA (AEE), the Puerto Rico Electric Power Authority, barred from negotiating another agreement to supply 400 megawatts of temporary generation from the Aguirre power plant (Central Aguirre).

According to El Vocero, as cited by NotiUno, the Board argued that Section 305 of the law Congress approved in June 2016 prohibits interference not only with the corporation’s revenues but also with its governance powers, its implementation of public policy and its use of property that produces monetary gains. The Board’s lawyers said Power Expectations is asking the court to set when and how PREPA may carry out one of its basic functions: procuring generation capacity to meet the electricity demand of the island’s residents.

In the Board’s words, if the court implemented the request, PREPA "would be prohibited from contracting with any other provider with temporary generation capacity at the Aguirre facility, thereby fulfilling its basic function of providing electricity to Puerto Rico, in favor of a party whose contract was cancelled on the instructions of the Oversight Board." The text also notes that the contract, valued at $5.9 billion, had been awarded to a consortium made up of Power Expectations LLC, Enchanted Rock and Reyes Contractor Group, and that eRock accused Power Expectations of threats, extortion and unauthorized use of signatures.

In context

SourceNotiUno