LUMA Energy will perform maintenance work on Sunday, causing temporary power outages in at least six municipalities in Puerto Rico. The work includes strengthening power poles and automating distributors to enhance the resilience of the power grid.
The majority of the work is expected to start around 8:00 AM. The affected municipalities are Cabo Rojo, Lares, Caguas, Trujillo Alto, San Juan, and Utuado.
LUMA announced the work through their website and social media, stating that while the work is necessary to reinforce the grid, it may cause temporary interruptions.
In context (787daily, from public data)
1.7%of LUMA customers without power
78-day average 0.3% · worst 3.5%, Nov 14
LUMA's portal showed 1.7% of customers out at 6:05 AM AST on Nov 23, 2026. Across the 78 days 787daily has tracked it, the daily average is 0.3% and the worst was 3.5% on Nov 14, 2026.
Worst of LUMA's five full years, up from 26.3 hours the year before
Customers averaged 27.6 hours without power in the fiscal year that ended in June 2026, the worst of the five full years LUMA has run the grid and up from 26.3 hours the year before.