PREPA and Energiza Dispute Interconnection Costs for New San Juan Bay Power Plant

Published Sep 10, 2026, 7:00 AM ASTvia El Nuevo Día

At a glance

  • PREPA and Energiza consortium are in dispute over $168 million in interconnection costs
  • The new power generation plant will produce 528 MW
  • The project’s operational start date has been delayed until the end of 2030

Why this matters: The delay and cost issues with the new power plant and transmission grid upgrades may impact the reliability and cost of electricity for Puerto Rican households and businesses.

Our coverage

Power live: 7,068 customers out island-wide at 9:13 AM

Puerto Rico’s Electric Power Authority (PREPA) and the private consortium Energiza are at odds over how to split an estimated $168 million cost for transmission grid upgrades. These upgrades are needed to allow the electric grid to absorb 528 megawatts of power that will be produced by a new generating plant planned near San Juan Bay.

The dispute centers specifically on which party—PREPA or Energiza—will bear responsibility for financing the transmission improvements required to connect the new plant to the existing grid.

In context (787daily, from public data)

SourceEl Nuevo Día

Follow this story

Our coverage

Power live: 7,068 customers out island-wide at 9:13 AM

  1. · El Nuevo DíaPREPA Seeks Dismissal of Power Expectations Lawsuit Over Generation Contract

More in Infrastructure