Puerto Rico Senate Hears Plans for Vieques Ferry Pier, New Bus Routes and Tren Urbano Study

Published Oct 28, 2026, 6:00 AM ASTvia The Weekly Journal

Also reported by NotiCel.

At a glance

  • ATI expects to publish the Mosquito Pier ferry request for proposals in January 2027, award the contract in May, and build from June 2027 through 2028, cutting travel time to Vieques by about 30 minutes.
  • Ferry fares for Vieques and Culebra residents stay at $2 and $2.50 respectively, while visitors pay $11.50 each way plus the environmental fee.
  • Puerto Rico won a $10 million federal award, the third jurisdiction in the competitive process, for Tren Urbano expansion studies toward San Juan and Carolina, with about $1 million local match and a federal agreement expected in December 2026.

Why this matters: Residents of Vieques and Culebra, who depend on the ferries for work, medical appointments and education, keep their $2 and $2.50 fares, while a Mosquito Pier short route could cut about 30 minutes off travel to Vieques.

Our coverage

The ferry schedule: the next boat to Vieques and Culebra

Puerto Rico’s Integrated Transportation Authority (ATI) updated the Puerto Rico Senate’s Committee on Transportation, Telecommunications, Public Utilities and Consumer Affairs on ferry fares, port projects and transit expansion at a public hearing on Tuesday. The commission is chaired by Carolina District Sen. Héctor Joaquín Sánchez Álvarez. ATI Executive Director Josué Menéndez Agosto said the new maritime transportation regulation includes recommendations from the mayors of Vieques and Culebra and members of the Legislature.

Resident fares to Vieques and Culebra stay at $2 and $2.50, while visitors pay $11.50 each way plus the environmental fee. For the proposed short-route ferry to Vieques via Mosquito Pier, ATI expects authorizations from the U.S. Army Corps of Engineers and other agencies in the coming months, then review by the Federal Transit Administration.

The preliminary schedule calls for a request for proposals in January 2027, a contract award in May and construction starting in June 2027 and running through 2028, subject to permits. The project could cut travel time to Vieques by about 30 minutes. Under its Intercity program, ATI plans a route linking Ceiba with the Piñero Tren Urbano station, and is evaluating routes to Utuado (stopping in Manatí) and Ponce (stopping in Cayey).

Puerto Rico also won a $10 million federal award for studies on extending the Tren Urbano toward San Juan and Carolina, with about $1 million in local matching funds (10%). A collaborative agreement with the U.S. Department of Transportation is expected in December 2026. HMS Ferries Puerto Rico announced terminal renovations in Old San Juan, Hato Rey and Cataño.